The delivery of the infrastructure improvements at Lochmaddy Pier have been impacted by the technical complexities associated with the caisson works, Comhairle nan Eilean Siar has said.
The improvements at the port, being undertaken by George Leslie Ltd on behalf of Comhairle nan Eilean Siar and Transport Scotland, include the extension of the pier. This is being achieved by the installation of a 33m long reinforced concrete caisson which was constructed in the Belfast dry-dock and towed to its temporary location within Lochmaddy Harbour at the beginning of September.
The Contractor has since been installing the permanent fenders and other equipment to the caisson and preparing the seabed at the end of the existing pier to enable the caisson to be moved to its final location.
The installation process faces a number of technical and operational constraints, such as tidal conditions, inclement weather, reducing daylight hours and increased ferry movements within the port due to the closure of the Lochboisdale linkspan in October, all whilst minimising the risk of disruption to the lifeline ferry service.
Given these challenges, and subject to there being a suitable "weather window", it is now envisaged that the caisson will be towed into its permanent position in January.
The project delivery team continue to liaise with CalMac to ensure that any risk of disruption to the ferry service is kept to an absolute minimum.
Updates will be provided to the communities in the Uists in the coming weeks as a final date for the movement of the caisson to its permanent location is agreed.
Construction News
29/11/2022
Infrastructure Improvements Works At Lochmaddy Pier


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip