SSEN Transmission has announced that the second of two major components in the development of Rothienorman Substation is set to arrive at the site this weekend.
Following on from the successful arrival of the first transformer in October, the SSEN Transmission team is gearing up for the delivery of the final transformer to Rothienorman Substation as part of the second phase of major work at the development.
Working with principal contractor Balfour Beatty, the project involves upgrading the existing infrastructure at the substation from 275 kilovolts (kV) to 400kV, this increased capacity will help accommodate the connection of more renewable generation from across the north of Scotland, playing a key role in the transition to net zero emissions.
As part of this, two surpergrid transformers - each weighing around 130 tonnes - along with the associated equipment and components will be installed at Rothienorman Substation, with the first of the units successfully delivered in October.
The next transformer will be delivered on Sunday 13 November and will follow the same format as the first delivery, with specialist haulier Rawcliffe transporting the 130-tonne unit via convoy using a large 12-axle specialist vehicle under the guidance and supervision of Police Scotland. The transformer will depart from Aberdeen Quay at 8am and make its way to Rothienorman substation via the A96, A920 and B992.
Due to the size of the transformer, the delivery vehicle will be travelling at a reduced speed for safety, and it is expected the journey will take between three and five hours. No road closures are required to facilitate the movement of the transformers, and vehicles should be able to pass the convoy at regular opportunities on the road network under guidance from Police Scotland, when safe to do so.
SSEN Transmission Project Manager Arthur Sinakov said: "We're gearing up for the second and final delivery of our major supergrid transformers, which are key components in our ongoing Phase Two development at Rothienorman Substation.
"The first transformer was successfully delivered with minimal impact to road users last month, and safely arrived at the site in just under three hours from Aberdeen Quay. The second unit will be delivered in the exact same planned route as before, and we aim to complete the complex delivery as quickly and safely as we can.
"As ever we want to thank the local community in advance for their patience and understanding while we transport these transformers onto their final location in Rothienorman."
Construction of the substation, located around two miles west of the village of Rothienorman, began with Phase one in 2019, and is part of a wider strategy to reinforce the transmission network in the North East and East Coast of Scotland to accommodate increased renewable energy generation, helping to deliver a network for net zero.
Construction News
10/11/2022
Latest Phase Of Rothienorman Substation Development Set To Begin


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont