SSE has announced that the first 100km of subsea cable has been successfully installed in the North Sea as part of SSEN Transmission's landmark Shetland High Voltage Direct-Current (HVDC) link project.
The £660 million project will involve constructing a 260km subsea cable from Shetland to the GB mainland, linking Shetland to the national grid for the first time, as well as unlocking Shetland's potential for future renewable energy generation.
Starting in July, the subsea HVDC cable was successfully pulled-in to where it makes landfall at Noss Head near Wick from aboard the specialist cable-laying vessel NKT Victoria, and was carefully installed onto the seabed as the vessel made its way out to sea to a point east of the Orkney Isles. Once the cable was installed on the seabed, where possible it was trenched into position using Grand Canyon III, a multi-role construction support vessel with a specialist subsea jet trencher.
The successful installation of the first 100km of cable required careful coordination between the NKT Victoria, multiple subsea divers as well as the shoreside cable pull-in team at Caithness, who worked to install the cable through the previously constructed horizontal directional drilled (HDD) ducts at Noss Head in Caithness.
Back onshore, teams have also completed the installation of the HVDC cables in Shetland, marking another major milestone for the project with all onshore HVDC cables now installed.
The offshore team is now focusing on readiness for next year's subsea cable installation campaigns, with the second campaign expected to begin in the spring. This will involve another 57km of cable from Weisdale Voe on Shetland heading south into the North Sea. The third campaign will take place later in 2023, which will complete the link between the first and second campaigns in the North Sea to join all three campaigns together and complete the full 260km subsea HVDC link.
Chris Finnigan, SSEN Transmission Lead Project Manager, said: "We're delighted that the first cable laying campaign is complete, meaning the first 100km of the Shetland HVDC link subsea cable has safely been installed on the seabed heading north from the Noss Head shore. It has been a complex operation involving multiple parties, and we're really pleased that this first campaign has been completed safely and successfully."
Chris continued: "At the same time the team has successfully completed the land cable installation works between the shoreline at Noss Head to the new HVDC Switching Station as well as on Shetland, marking a huge achievement and a massive milestone for the project.
"It's another significant leap forward for the Shetland HVDC link project and builds further on the excellent progress to date.
"The HVDC technology being used to connect Shetland to the GB mainland transmission system provides the most efficient and reliable means of transmitting large amounts of power over long distances via subsea. To reach this stage follows on from years of design work to ensure the cable has robust protection against any damage, including where possible burying the cable in the seabed and installing rock protection where trenching cannot be achieved. Our focus is now on completing the rock placement scope and planning for next year's subsea cable installation campaigns.
"As always, we thank the local community and stakeholders both onshore and offshore respectively for their cooperation and understanding while we continue with this crucial project, and as ever we'll work to keep them informed as we move through the phases of the Shetland HDVC link project."
The Shetland HVDC subsea link project is on track to be completed by 2024.
Construction News
02/11/2022
First 100km Of Subsea Cable Installed In Shetland HVDC Project


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip