Network Rail has announced that they are set to begin works to lay the foundations for the electrification of the Levenmouth Rail Link.
The first phase of work between Thornton Junction and Haugh Mill Lade will see the project pile foundations for masts that will carry overhead wires in readiness for the introduction of quieter and more environmentally friendly electric trains.
Work to install the piles will begin on Monday October 24 and will last for circa three weeks as the first piles are inserted to the west of the rail corridor - mostly during day-time working. One night of overnight piling will be required for locations closest to Thornton Junction and this is scheduled for Saturday October 29.
Further piling along the Levenmouth rail corridor is being programmed so that it works in tandem with other activities on the project, such as work on bridges and track laying.
Piling is an essential part of laying the foundations for the newly electrified railway and it is among the noisiest work activities on the railway and can be disruptive. Homes closest to the work sites have been notified by letter to make them aware of the possible noise.
While the work is being delivered as part of the reinstatement of the branch, electrification of the line to Leven is part of the wider electrification of the railway in Fife as part of the Scottish Government's plan to decarbonise passenger services on the network by 2035.
Work on the Levenmouth Rail Link is scheduled to complete in spring 2024 and services will initially be in introduced using diesel trains. By this point however, the line will be future-proofed to enable the introduction of Battery Electric Multiple Units (BEMUs) to replace life-expired diesel units which will be phased out on completion of the wider Fife electrification project.
Sean Clemie, earthworks and structures lead for the project said: "The first piles going into the ground in the Thornton area is big for the project but also an important milestone for the wider aspirations to decarbonise the railway across Fife.
"With the first mile of the Leven branch already operational railway, we can use this to move the track-based piling rig to each location to sink the foundations and then insert the masts that will ultimately carry the overhead wires that will power the railway.
"The start of this phase of work is another sign that the project is really taking shape. It's an exciting step forward for the team as we work towards delivering an electrified railway for Levenmouth and in creating an even greener, cleaner, and more reliable railway for Scotland."
Time and date
CONSTRUCTION DIRECTORY
Construction News
18/10/2022
Levenmouth Rail Link Electrification Works To Get Underway
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...