SSE Renewables has completed the successful installation of almost 73 miles of HVDC underground cables in another "giant milestone" in the development of Dogger Bank Wind Farm.
Onshore construction for the first two phases of Dogger Bank Wind Farm began in January 2020 when Jones Bros Civil Engineering broke ground near the village of Ulrome in East Riding of Yorkshire.
The North Wales civil engineering specialists have installed almost 73 miles of HVDC cables in East Riding, with support from Bristol-based Power Systems UK and North Yorkshire cable installation specialists F B Taylor.
Jones Bros commenced installation of the cable ducting system in spring 2020, with the support of Essex-based Joseph Gallagher undertaking a series of horizontal directional drills in preparation for cable installation works to begin last summer.
This latest milestone marks the completion of HVDC cable installation work in East Riding, with the team now focusing on the installation of around four miles of HVAC cable from its convertor station site near Beverley, to the Creyke Beck electricity sub-station near Cottingham.
Work is also underway to reinstate the land to its former condition, following completion of this part of the programme.
Onshore project manager for Dogger Bank Wind Farm, Oliver Flattery, said: "The whole team has worked incredibly hard and diligently since the start of 2020 to safely and efficiently prepare the 30km route, through a combination of trenching and drilling methods, before installing protective ducts and then feeding 3,362 tonnes of underground cables through these ducts.
"This has been a huge undertaking, and one we're all proud to have been part of.
"We thank local residents and businesses in East Riding of Yorkshire for their patience and understanding over the last 2 years while this work has been taking place."
Dogger Bank Wind Farm is being built in the North Sea more than 130km from the Yorkshire coast in three phases known as Dogger Bank A, B and C. Dogger Bank A and B phases will connect to the national grid near Beverley in East Riding of Yorkshire, while Dogger Bank C will connect to the grid near Redcar in the Tees Valley.
The world-class renewable energy project, which will be capable of powering 6 million UK homes annually on completion, is a joint venture between SSE Renewables (40%), Equinor (40%) and Eni Plenitude (20%).
The electricity generated by the Dogger Bank A and B wind turbines will come ashore south of Bridlington at Ulrome in East Riding, and be transmitted via underground HVDC cables to the onshore convertor station site in East Riding.
The HVDC cable route ends at the convertor station site near Beverley, where two convertor stations are currently under construction. Here, the electricity will be converted from HVDC to HVAC current for transmission to homes and businesses via the UK grid network.
The Dogger Bank project is the first offshore wind farm in the UK to use HVDC technology, which allows electricity to be transmitted efficiently across long distances.
Jones Bros project manager James Lockwood said: "Hitting this key milestone on the world's largest offshore wind farm has been made possible thanks to the efforts of every individual on site.
"I know it brings everyone from senior managers to trainees and apprentices a great sense of pride to be associated with this project, and we're excited to see how the rest of the scheme develops."
Nigel Baldwin, Health and Safety Director for F B Taylor, said: "Working on the largest offshore wind farm has been a humbling experience for all involved and something that we are immensely proud of. We would like to thank the full site team for their work ethic and support during this project and hope to be involved with many more offshore opportunities throughout the coming years."
Jonathan Stock, Head of Projects for Powersystems UK, said: "We are very pleased to announce the completion of the HVDC cable installation at Dogger Bank Wind Farm, the world's largest offshore windfarm. This is a huge achievement for all involved and particularly the efforts of the Powersystems UK team, our supply chain partners FB Taylors and Collett Transport and partners Jones Bros.
"The team showed great pride, professionalism, proactiveness, partnership and priority towards health, safety, environment, and quality."
Tony Matheson, Director at Joseph Gallagher Limited, said: "This has been a fantastic project to work on over the past two years. Our team have been instrumental throughout, operating four horizontal directional drilling rigs simultaneously during peak times, installing an impressive 27km of duct in 140 drills – ranging from 50m to 620m and then returning to grout the cables after the install.
"It's been a true collaborative effort working with Jones Bros throughout the project. The team's work ethic shone through helping to deliver the project to programme and with safety at the forefront - something we are very proud to have been part of."
Offshore construction work on the first two phases of the project began in April with the start of work to install sub-sea HVDC cables off the Yorkshire coast. And in July the project celebrated the successful installation of the first foundation in the North Sea. Next year the team will install the first turbine on Dogger Bank A, with a total 277 GE Renewable Energy Haliade-X turbines set to be installed on all three phases of the project by 2026.
Onshore work is also underway on the third phase of the windfarm in the Tees Valley, where the project is collaborating with neighbouring Sofia Offshore Wind Farm, owned by RWE, to minimise disruption to the local community.
Construction News
21/09/2022
'Giant Milestone' In Dogger Bank Wind Farm Development


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont