'Giant Milestone' In Dogger Bank Wind Farm Development

Construction News Image
SSE Renewables has completed the successful installation of almost 73 miles of HVDC underground cables in another "giant milestone" in the development of Dogger Bank Wind Farm.

Onshore construction for the first two phases of Dogger Bank Wind Farm began in January 2020 when Jones Bros Civil Engineering broke ground near the village of Ulrome in East Riding of Yorkshire.

The North Wales civil engineering specialists have installed almost 73 miles of HVDC cables in East Riding, with support from Bristol-based Power Systems UK and North Yorkshire cable installation specialists F B Taylor.

Jones Bros commenced installation of the cable ducting system in spring 2020, with the support of Essex-based Joseph Gallagher undertaking a series of horizontal directional drills in preparation for cable installation works to begin last summer.

This latest milestone marks the completion of HVDC cable installation work in East Riding, with the team now focusing on the installation of around four miles of HVAC cable from its convertor station site near Beverley, to the Creyke Beck electricity sub-station near Cottingham.

Work is also underway to reinstate the land to its former condition, following completion of this part of the programme.

Onshore project manager for Dogger Bank Wind Farm, Oliver Flattery, said: "The whole team has worked incredibly hard and diligently since the start of 2020 to safely and efficiently prepare the 30km route, through a combination of trenching and drilling methods, before installing protective ducts and then feeding 3,362 tonnes of underground cables through these ducts.

"This has been a huge undertaking, and one we're all proud to have been part of.

"We thank local residents and businesses in East Riding of Yorkshire for their patience and understanding over the last 2 years while this work has been taking place."

Dogger Bank Wind Farm is being built in the North Sea more than 130km from the Yorkshire coast in three phases known as Dogger Bank A, B and C. Dogger Bank A and B phases will connect to the national grid near Beverley in East Riding of Yorkshire, while Dogger Bank C will connect to the grid near Redcar in the Tees Valley.

-- Advertisement --
NorthernAsbestosServicesLtd

The world-class renewable energy project, which will be capable of powering 6 million UK homes annually on completion, is a joint venture between SSE Renewables (40%), Equinor (40%) and Eni Plenitude (20%).

The electricity generated by the Dogger Bank A and B wind turbines will come ashore south of Bridlington at Ulrome in East Riding, and be transmitted via underground HVDC cables to the onshore convertor station site in East Riding.

The HVDC cable route ends at the convertor station site near Beverley, where two convertor stations are currently under construction. Here, the electricity will be converted from HVDC to HVAC current for transmission to homes and businesses via the UK grid network.

The Dogger Bank project is the first offshore wind farm in the UK to use HVDC technology, which allows electricity to be transmitted efficiently across long distances.

Jones Bros project manager James Lockwood said: "Hitting this key milestone on the world's largest offshore wind farm has been made possible thanks to the efforts of every individual on site.

"I know it brings everyone from senior managers to trainees and apprentices a great sense of pride to be associated with this project, and we're excited to see how the rest of the scheme develops."

Nigel Baldwin, Health and Safety Director for F B Taylor, said: "Working on the largest offshore wind farm has been a humbling experience for all involved and something that we are immensely proud of. We would like to thank the full site team for their work ethic and support during this project and hope to be involved with many more offshore opportunities throughout the coming years."

Jonathan Stock, Head of Projects for Powersystems UK, said: "We are very pleased to announce the completion of the HVDC cable installation at Dogger Bank Wind Farm, the world's largest offshore windfarm. This is a huge achievement for all involved and particularly the efforts of the Powersystems UK team, our supply chain partners FB Taylors and Collett Transport and partners Jones Bros.

"The team showed great pride, professionalism, proactiveness, partnership and priority towards health, safety, environment, and quality."

Tony Matheson, Director at Joseph Gallagher Limited, said: "This has been a fantastic project to work on over the past two years. Our team have been instrumental throughout, operating four horizontal directional drilling rigs simultaneously during peak times, installing an impressive 27km of duct in 140 drills – ranging from 50m to 620m and then returning to grout the cables after the install.

"It's been a true collaborative effort working with Jones Bros throughout the project. The team's work ethic shone through helping to deliver the project to programme and with safety at the forefront - something we are very proud to have been part of."

Offshore construction work on the first two phases of the project began in April with the start of work to install sub-sea HVDC cables off the Yorkshire coast. And in July the project celebrated the successful installation of the first foundation in the North Sea. Next year the team will install the first turbine on Dogger Bank A, with a total 277 GE Renewable Energy Haliade-X turbines set to be installed on all three phases of the project by 2026.

Onshore work is also underway on the third phase of the windfarm in the Tees Valley, where the project is collaborating with neighbouring Sofia Offshore Wind Farm, owned by RWE, to minimise disruption to the local community.

Latest Construction News

03/01/2025

Insurepair, the Edinburgh-based all trades insurance reinstatement specialist, is to launch an ambitious business strategy. The firm will invest £100,000 in new technology over the next 12 months. Insurepair will adopt CoreLogic's Symbility® platform, an industry-leading property insurance claim ...
03/01/2025

Kier has completed construction of a new surgical centre at NHS Golden Jubilee in Clydebank. The centre will increase the hospital's patient capacity and enable the treatment of thousands of people waiting for vital care and procedures. Scottish First Minister, John Swinney, visited the project ...
03/01/2025

Clark Contracts recently hosted a behind-the-scenes look at the major redevelopment works at Bught Park in Inverness. The main contractor is refurbishing the B-listed grandstand and constructing a new pavilion and shinty museum. Work is now focused on completing the pavilion's interior fit-out. ...
03/01/2025

CCG Group has officially opened a new 25,000 sq ft window and door manufacturing facility in Cambuslang. The facility is part of a wider £6 million investment by CCG. It will fabricate a range of enhanced window and door sets and employ 60 skilled workers. CCG has been manufacturing window and ...
03/01/2025

Work on a £50 million redevelopment of Aberdeen beachfront is set to begin in earnest after the festive break. Construction teams will be on site immediately after Christmas to start work on the first main features of the project. Aberdeen City Council's Co-Leaders have welcomed the move. The ...
03/01/2025

The iconic gasholder in north Edinburgh, now named 'Gas Holder 1', is now permanently illuminated after dark. Refurbishment on the structure, funded by the UK Government, is complete. The frame is now lit brightly in the twilight hours and will remain lit in festive colours throughout ...
02/01/2025

SSE has made a final investment decision to proceed with the construction of its 208MW Strathy South onshore wind farm in the Scottish Highlands. Located in north-east Sutherland, the wind farm has been in development for over a decade. Once completed, it is expected to generate enough renewable ...
02/01/2025

A range of organisations supporting vulnerable communities across Scotland have received funding from SP Energy Networks' Net Zero Fund. The grants will enable these groups to implement projects that decarbonise their operations and accelerate their journey towards net zero emissions. Projects ...
02/01/2025

The first phase of a £10 million project to upgrade a strategic sewer main between Renfrew and Glasgow has been completed. Nearly a kilometre of pipe running beneath King's Inch Road has been relined, creating a new pipe within the existing one. Robert Archer, Scottish Water Alliance Manager, ...
02/01/2025

Two new transformers have arrived at the Errochty Grid Supply Point in Highland Perthshire. This marks a significant milestone in the project to upgrade the electricity network in the region. The 90MVA 132/33kV transformers were transported to the site following a carefully planned operation that ...
Morris & Spottiswood LtdRBT Underfloor LimitedToner Damp Proofing SuppliesNo HydroMaccaferri LtdBurnside Plant Hire LtdM K M Building Supplies LtdAlternative Tying Systems LtdContainexPerthshire Joinery Ltd
Terms and Conditions
2025/01/05 00:27:30