05/09/2022

Vital Upgrade Works Approved For Uig Harbour

Construction News Image
Transport Scotland has announced a revised programme of vital works to upgrade Uig Harbour following detailed consultation with local communities and project partners.

The planned outage has been reduced from 24 weeks to 14 weeks and will be split over two periods, helping to reduce disruption to communities during the works.

The first outage will commence on 16 January 2023 until 13 March 2023, and the second outage will commence on 30 October 2023 until 11 December 2023. These changes are being supported by direct investment of £6 million from the Scottish Government.

Minister for Transport Jenny Gilruth said: "It was very clear in my meetings with Western Isles stakeholders earlier this year that the original plans for the Uig outage were not acceptable to island communities. Having convened a number of resilience calls with islanders and stakeholders, I am pleased that we have been able to reach this resolution, which is supported by additional funding from the Scottish Government.

"I appreciate that any level of disruption is not welcome, but this project is vital to improving ferry services and the harbour experience in Uig in the longer term.

-- Advertisement --
NorthernAsbestosServicesLtd

"I would like to thank The Highland Council, CalMac, CMAL, Western Isles Council, Harris Development Ltd, Harris Transport Forum, local elected members and members of the Ferries Community Board for their co-operation in the series of meetings which have led to this outcome. I will continue to urge project partners to look at reducing the duration of the outages if possible."

The project is being led by Highland Council. Malcolm MacLeod, Executive Chief Officer of Infrastructure, Environment and Economy, said: "The first outage period will enable the installation of some of the permanent infrastructure as well as the installation of a temporary bridge to enable the ferry services to resume for the summer timetable next year. The new linkspan will then be installed during the second outage with completion over the Uig upgrades works now expected to be Spring 2024.

"We continue to work to minimise disruption during the works and, when complete, will provide improved marshalling and ferry terminal facilities as well as the ability to cater for large ferry vessels serving the route in the future."

Highland Council Leader, Cllr Raymond Bremner, said: "We are pleased to have been able to find a workable solution that reduces the impact of the much-needed replacement berthing facilities and improvements at Uig Harbour.

"We will continue to work with our partners to ensure the safe and efficient operation of the harbour while the works are ongoing."

The community will be informed of further details of the construction works and traffic management arrangements through locally held liaison meetings over the next month and throughout the project via the Highland Council Project website.

Robbie Drummond, Managing Director of CalMac, said: "We recognise that the closure of Uig harbour by Highland Council will be disruptive to local communities, and I am very grateful for their patience while we finalised the required service changes.

"This has been an extremely complex operation, but we believe that we have provided the best available solution in order to maintain lifeline services."

Latest Construction News

14/11/2024

Brunstane Primary School in Edinburgh is set to undergo a significant £10 million transformation to become one of the greenest schools in the capital. Construction work, led by GRAHAM, commenced in October 2024 and is expected to be completed by winter 2025. The project involves a comprehensive ...
14/11/2024

Edinburgh City Council has approved an ambitious plan to guide the city's future development. City Plan 2030 outlines strategies to meet the needs of a growing population while protecting the city's heritage and environment. Key elements of the plan include: • Housing: The plan aims to deliver ...
14/11/2024

The CCG Group has taken a significant step towards sustainable construction by completing pioneering research into Whole-Life Carbon. This groundbreaking study provides crucial insights into the carbon emissions associated with the entire lifecycle of a building, from material extraction to ...
14/11/2024

Clark Contracts has been awarded a significant contract to undertake the deep retrofit of the building housing Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory for sustainable construction and energy ...
14/11/2024

Network Rail has successfully completed a £3.2 million investment programme to upgrade the West Highland Line. The four-day project, which ran from Saturday, 09 November, to the early hours of Wednesday, 13 November, involved extensive track renewals, structural repairs, and drainage improvements ...
14/11/2024

Dundashill Plot 3A, Scotland's largest Passivhaus-accredited residential development, has added another accolade to its list of achievements. The project recently won the CIH Housing Award for 'Excellence in Regeneration & Sustainability.' Located in north Glasgow, Dundashill Plot 3A is the first ...
14/11/2024

Glasgow City Council is set to transform a derelict site in Cadder into a 15-hectare woodland. The new green space will provide valuable habitat for wildlife, recreational opportunities, and outdoor learning experiences for the local community. The council has also secured funding to establish a ...
14/11/2024

HFD, Scotland's leading commercial property company, has appointed Chris McGhee as the new commercial lead for its construction business. With over 25 years of industry experience, McGhee will play a pivotal role in delivering high-quality, sustainable building projects across Scotland. McGhee ...
14/11/2024

SSEN Transmission employees recently joined forces with Friends of Loch Lomond and The Trossachs to contribute to the upkeep of the Three Lochs Way path in the Arrochar area. As part of their commitment to community engagement, the volunteers spent a day clearing overgrown vegetation and improving ...
14/11/2024

The Association for Project Safety (APS) has launched a nationwide campaign to address the pressing issue of mental health within the construction industry. The campaign aims to raise awareness, reduce stigma, and provide support to construction workers who are struggling with mental health ...
RBT Underfloor LimitedMorris & Spottiswood LtdDW Joiners LtdSEEIT3DCF Concrete PumpingMaccaferri LtdSMS Alba LimitedDiscount Kitchens and Bathrooms LtdShopfronts ScotlandJSJ Foam Insulation Ltd
Terms and Conditions
2024/11/14 20:14:21