Vital Upgrade Works Approved For Uig Harbour

Construction News Image
Transport Scotland has announced a revised programme of vital works to upgrade Uig Harbour following detailed consultation with local communities and project partners.

The planned outage has been reduced from 24 weeks to 14 weeks and will be split over two periods, helping to reduce disruption to communities during the works.

The first outage will commence on 16 January 2023 until 13 March 2023, and the second outage will commence on 30 October 2023 until 11 December 2023. These changes are being supported by direct investment of £6 million from the Scottish Government.

Minister for Transport Jenny Gilruth said: "It was very clear in my meetings with Western Isles stakeholders earlier this year that the original plans for the Uig outage were not acceptable to island communities. Having convened a number of resilience calls with islanders and stakeholders, I am pleased that we have been able to reach this resolution, which is supported by additional funding from the Scottish Government.

"I appreciate that any level of disruption is not welcome, but this project is vital to improving ferry services and the harbour experience in Uig in the longer term.
-- Advertisement --
NorthernAsbestosServicesLtd



"I would like to thank The Highland Council, CalMac, CMAL, Western Isles Council, Harris Development Ltd, Harris Transport Forum, local elected members and members of the Ferries Community Board for their co-operation in the series of meetings which have led to this outcome. I will continue to urge project partners to look at reducing the duration of the outages if possible."

The project is being led by Highland Council. Malcolm MacLeod, Executive Chief Officer of Infrastructure, Environment and Economy, said: "The first outage period will enable the installation of some of the permanent infrastructure as well as the installation of a temporary bridge to enable the ferry services to resume for the summer timetable next year. The new linkspan will then be installed during the second outage with completion over the Uig upgrades works now expected to be Spring 2024.

"We continue to work to minimise disruption during the works and, when complete, will provide improved marshalling and ferry terminal facilities as well as the ability to cater for large ferry vessels serving the route in the future."

Highland Council Leader, Cllr Raymond Bremner, said: "We are pleased to have been able to find a workable solution that reduces the impact of the much-needed replacement berthing facilities and improvements at Uig Harbour.

"We will continue to work with our partners to ensure the safe and efficient operation of the harbour while the works are ongoing."

The community will be informed of further details of the construction works and traffic management arrangements through locally held liaison meetings over the next month and throughout the project via the Highland Council Project website.

Robbie Drummond, Managing Director of CalMac, said: "We recognise that the closure of Uig harbour by Highland Council will be disruptive to local communities, and I am very grateful for their patience while we finalised the required service changes.

"This has been an extremely complex operation, but we believe that we have provided the best available solution in order to maintain lifeline services."

Latest Construction News

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment. The pane
15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire. The event will take place on Monday, 28 April, from 4 pm t
15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle. This key appointment will enable crucial work to progress on the project, including feasibility s
15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027. The £5 million
15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment. The practical guide is designed for landowners, developers,
15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it
14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year. The initial grant of £78.687 million from the Scottish Government
14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure. From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont
Morris & Spottiswood LtdRBT Underfloor LimitedNational Access & Scaffolding Confederation (NASC) - ScotlandAC Cable Solutions24-7 HealthcareThe Scottish Natural Insulation HubMaccaferri LtdPD ServicesMV CommercialSMS Alba Limited