Network Rail has announced that work to construct the new bridge over the railway at Nithsdale Road in Glasgow's Southside is now underway following successful demolition of the old structure.
The project, part of the Glasgow-Barrhead electrification works, will see a new bridge deck constructed higher over the railway to enable overhead electrification wires to run safely beneath the structure.
The bridge demolition is the latest phase of work within the Barrhead to Glasgow electrification project and is part of wider plans to decarbonise passenger services on Scotland's railway by 2035.
Working over two successive weekends while the railway was closed for 53 hours, contractors Bam Nuttall on behalf of Network Rail worked continuously to demolish and clear the old bridge before craning into place the first elements of the new structure.
Over the first weekend, 1,100 tonnes(t) of spoil, including seven wrought iron girders, were removed from the railway bridge using a 500t crane. The masonry brick work from the structure will be recycled and reused as cladding.
Over the second weekend, four concrete pre-cast cil units were craned into position on the abutments of the former structure using a 750t crane. These provide the additional height clearance needed for the electrification wires to run safely under what will also be a thinner bridge deck.
As work continues with the bridge and other elements of the electrification project, pedestrian access over the railway will continue via the nearby footbridge between Moray Place and Darnley Road, with temporary ramps fitted to allow step free access.
Allan Wilson, Network Rail's project manager for the Glasgow-Barrhead electrification said: "Successful demolition of the Nithsdale Road bridge removes a key blocker to the installation of the overhead wires that will enable the electrification of the line to Barrhead by December 2023.
"Closing the railway for consecutive weekends was the most efficient way to remove the structure and then to make good progress in the first stages of the construction of the new bridge by installing cil units on the abutments and the pre-cast beams which will form the framework of the new bridge deck.
"We will have the new deck in place in September and then will begin the process of reconnecting the utilities across the structure with a view to having completed the work and opening the new bridge in January next year.
"We are grateful to the local community and road users for their patience and cooperation during this work."
In addition to the main bridge works, the team took the opportunity to maximise the value of the railway closure by demolishing a smaller structure at Kennishead Road near Darnley and installing an under-track crossing to carry diverted power cables.
Construction News
24/08/2022
Glasgow Southside Rail Bridge Works Underway


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont