Network Rail has announced the successful completion of a £1.8 million programme of work to improve the resilience of the railway on the Mallaig line at Lochailort in the West Highlands.
Starting in February of this year, the work delivered by Network Rail and supply chain partner QTS followed on from previous activity undertaken at this location in the summer of 2020 – when severe weather caused flash floods that washed away 80 metres of railway.
The initial phase of the improvement work involved installing a new concrete drainage tunnel, or culvert, next to the existing Allt na Criche bridge that carries the Allt na Criche burn under the railway.
Engineers removed 800 tonnes of material from the existing railway embankment in preparation of the new culvert being installed. The majority of material removed was then recycled on site for other elements of work.
Installation of the 63.3 tonne culvert took place in the spring during a 78-hour period of continuous working. Four, precast culvert sections were installed in ten lifts using a 250-tonne crane to complete the task. The area was then backfilled with 450 tonnes of stone around the culvert to raise it back to track level.
The railway embankment was then reinstated before 40 metres of new rail was laid on 200 tonnes of new ballast.
A new Terramesh bund 112 metres in length, up to 2.3 metres in height and 5.3 metres wide at the base was then created to help to protect the railway and surrounding land from future flooding events.
Jeremy Spence, Network Rail’s programme manager for the work, said: "Our work on the Mallaig line at Lochailort was a significant undertaking, given the sheer size of the culvert and the scale of the excavation involved.
"The successful delivery of the work and the significant benefits this project delivers will help tackle severe weather incidents that are increasingly frequently presenting challenges to the railway industry.
"By protecting the railway from extreme weather events, we also mitigate the risk of the impact of this for passengers, freight customers and lineside neighbours.
"I would like to thank our contractor QTS as well as the local community for their patience and support while we delivered this critical improvement to Scotland’s Railway".
Andy Steel, QTS operations director, said: "The work carried out at Lochailort over the last five months has hugely improved the resilience of Scotland’s Railway for years to come.
"Our team undertook some important work during this period, including the installation of a structure that will help manage waterflow to safeguard the integrity of the railway during heavy rainfall.
"We appreciate the patience of the lineside neighbours and the travelling public during this works."
Construction News
09/08/2022
Network Rail Completes £1.8m Lochailort Works


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont