Scottish Water has announced that they are now within six months of completing the new £multimillion Water Treatment Works in Peebles.
The works, which was constructed off site by Ross-Shire Engineering at their factory in Muir of Ord, was transported nearly 200 miles by road in 17 sections. It is the largest of its kind in the UK and is crammed full of new water treatment technologies.
By building the works off-site, the team have been able to cut down the construction time, reduce the amount of construction traffic through the town and make savings on carbon.
Each of the 17 units, weighing up to 36 tonnes, were built to the largest width that could be transported by road without requiring closures. The units were escorted down the country by police and came through Peebles High Street, turning many heads as they slowly moved through the town.
Bringing loads like this through a historic town like Peebles was not easy. The tight corners tested the manoeuvrability of the specialist lorries to the extreme and the deliveries wouldn't have been possible without local residents kindly moving their cars before each delivery.
Daniel Sutherland from Ross-Shire Engineering said: "This is the largest transportable treatment works ever built in the UK and getting it to site from our factory up North has been a real logistics challenge. It is brilliant to finally see the building in situ and to start the six-month countdown to it supplying water to the town."
The works, which is supplied with water from Megget Reservoir 18km away, houses four CeraMac Membranes which are able to effectively and efficiently treat large volumes of water to the highest standards. These membranes work by pushing the water through tiny holes which are many times smaller than a human hair, helping them to catch the smallest impurities in the water.
Keeping the carbon emissions down has been a key priority for the project team. Rather than removing soil from the site during construction, it has been used to help the works blend into the landscape and has helped to reduce the amount of site traffic. On the building's roof, 50MWh of solar panels have been installed to help power the site.
John Shaw, Project Manager for the works, said: "The innovative technologies which have gone into this building are very impressive. From the construction methods, to the treatment equipment and the renewables, this has been one of the most exciting projects I have been involved in. I can't wait to see it up and running."
Over the next six months, the outside the works will slowly blend into its surroundings through the planting of trees, wildflowers and further landscaping. Inside the building, engineers will be getting the new works ready to seamlessly switch over supply to customers in the area.
Construction News
24/06/2022
New Peebles Water Treatment Works Nearing Completion


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont