Network Rail has announced that the route between Rutherglen and Exhibition Centre has re-opened following a £32m improvement project.
Having successfully completed work to the Argyle line, which will reopen as planned today, Monday May 9, following an eight-week programme of extensive engineering works.
The line closed on March 13 to allow engineers to deliver a £32m investment in repairing and renewing tunnels, bridges and tracks between Rutherglen and Exhibition Centre
It was the most significant piece of engineering on the line in a generation and was all designed to improve punctuality and reliability for passengers for years to come.
Engineers removed 500 tonnes of concrete encasement from the tunnels, with 700 structural beams repainted and more than 1,000 square metres of waterproofing applied.
All ScotRail services affected by the work resumed in time for the start of Monday morning service.
Jenny Gilruth, Transport Minister, said: "Passengers will undoubtedly welcome the news that this particular programme of work and its associated closures have come to an end. I’d like to thank them for their patience throughout, particularly users of Anderston station. I would also like to thank all of the staff at Network Rail and ScotRail who have facilitated these improvements, delivering them on time and within budget.
"The Scottish Government has provided £32m of funding for this work and will continue to significantly invest in rail infrastructure and services in Scotland which helps us to attract passengers back to rail. It is vital that we deliver reliable infrastructure and do so in a manner that minimises the impact of disruption to passengers and freight.
"Any project of this scale brings with it a number of challenges but at the same time also delivers significant improvements to Scotland’s Railway for passengers, including a reduction in the need for future disruption arising from any future works.
Jeremy Spence, programme manager, Network Rail, said: "I am pleased that this major programme of work to the Argyle line has been completed both on time and within budget.
"The complexity of a project that covers multiple work sites, involves a range of disciplines, not to mention the mobilisation of plant and equipment, is not without significant challenges. It’s a credit to the Network Rail project team, our contractors and supply chain partners that every element was delivered safely and on time.
"The outcome is a comprehensive programme of improvements and enhancements that futureproof Scotland’s Railway for passengers, as work on this scale will not be required for many years to come.
"Closing part of our infrastructure is something done rarely, as we fully appreciate the impact of this on our customers. Our decision was weighed against whether it was best to complete the work over an intense period of time by closing the line completely or prolong it over many months by only being able to undertake work at weekends.
"I would like to thank all the passengers whose travel plans have been affected for their patience and understanding over the past eight weeks."
David Simpson, ScotRail Service Delivery Director, said: "This was an ambitious programme of work and it’s great to see that it’s been completed on time, within budget, and with alternative transport arrangements working well for customers.
"The work has helped future proof the line and customers can look forward to a better journey experience.
"We’d ask them for a little bit more patience as we carry out further essential work at Anderston station over the next four weeks.
"We’ll be upgrading the entrance, booking office, concourse and platforms and installing a lift for better customer access.
"This is all part of our strategy to make ScotRail fit for the future with investment in infrastructure, more reliable timetables, and great offers like the half-price ticket sale which begins on 9 May."
The Argyle line project includes improvements to Anderston station, with the closure of the station extended by four weeks until June 6. This is to allow engineers to complete critical work on the entrance, booking office, concourse and platforms.
By extending the closure, the most critical work will be finished earlier and reduces the overall time taken to renovate the station by 12 weeks, completing in the autumn instead of by December 2022.
Once complete, the station will feature a lift for better customer access, a remodelled booking office and modern finishes on the stairs, floors and ceilings. This also includes improving the outside area to the station, with a new-look glazed entrance and enhanced external lighting.
Time and date
CONSTRUCTION DIRECTORY
Construction News
09/05/2022
Network Rail Completes £32m Rutherglen Improvement Project
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...