Network Rail has announced that the route between Rutherglen and Exhibition Centre has re-opened following a £32m improvement project.
Having successfully completed work to the Argyle line, which will reopen as planned today, Monday May 9, following an eight-week programme of extensive engineering works.
The line closed on March 13 to allow engineers to deliver a £32m investment in repairing and renewing tunnels, bridges and tracks between Rutherglen and Exhibition Centre
It was the most significant piece of engineering on the line in a generation and was all designed to improve punctuality and reliability for passengers for years to come.
Engineers removed 500 tonnes of concrete encasement from the tunnels, with 700 structural beams repainted and more than 1,000 square metres of waterproofing applied.
All ScotRail services affected by the work resumed in time for the start of Monday morning service.
Jenny Gilruth, Transport Minister, said: "Passengers will undoubtedly welcome the news that this particular programme of work and its associated closures have come to an end. I’d like to thank them for their patience throughout, particularly users of Anderston station. I would also like to thank all of the staff at Network Rail and ScotRail who have facilitated these improvements, delivering them on time and within budget.
"The Scottish Government has provided £32m of funding for this work and will continue to significantly invest in rail infrastructure and services in Scotland which helps us to attract passengers back to rail. It is vital that we deliver reliable infrastructure and do so in a manner that minimises the impact of disruption to passengers and freight.
"Any project of this scale brings with it a number of challenges but at the same time also delivers significant improvements to Scotland’s Railway for passengers, including a reduction in the need for future disruption arising from any future works.
Jeremy Spence, programme manager, Network Rail, said: "I am pleased that this major programme of work to the Argyle line has been completed both on time and within budget.
"The complexity of a project that covers multiple work sites, involves a range of disciplines, not to mention the mobilisation of plant and equipment, is not without significant challenges. It’s a credit to the Network Rail project team, our contractors and supply chain partners that every element was delivered safely and on time.
"The outcome is a comprehensive programme of improvements and enhancements that futureproof Scotland’s Railway for passengers, as work on this scale will not be required for many years to come.
"Closing part of our infrastructure is something done rarely, as we fully appreciate the impact of this on our customers. Our decision was weighed against whether it was best to complete the work over an intense period of time by closing the line completely or prolong it over many months by only being able to undertake work at weekends.
"I would like to thank all the passengers whose travel plans have been affected for their patience and understanding over the past eight weeks."
David Simpson, ScotRail Service Delivery Director, said: "This was an ambitious programme of work and it’s great to see that it’s been completed on time, within budget, and with alternative transport arrangements working well for customers.
"The work has helped future proof the line and customers can look forward to a better journey experience.
"We’d ask them for a little bit more patience as we carry out further essential work at Anderston station over the next four weeks.
"We’ll be upgrading the entrance, booking office, concourse and platforms and installing a lift for better customer access.
"This is all part of our strategy to make ScotRail fit for the future with investment in infrastructure, more reliable timetables, and great offers like the half-price ticket sale which begins on 9 May."
The Argyle line project includes improvements to Anderston station, with the closure of the station extended by four weeks until June 6. This is to allow engineers to complete critical work on the entrance, booking office, concourse and platforms.
By extending the closure, the most critical work will be finished earlier and reduces the overall time taken to renovate the station by 12 weeks, completing in the autumn instead of by December 2022.
Once complete, the station will feature a lift for better customer access, a remodelled booking office and modern finishes on the stairs, floors and ceilings. This also includes improving the outside area to the station, with a new-look glazed entrance and enhanced external lighting.
Construction News
09/05/2022
Network Rail Completes £32m Rutherglen Improvement Project


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip