Network Rail has welcomed the progress being made to reinstate the Levenmouth Rail link, with "various elements of work springing up across the route".
Network Rail said that with the proximity of the river and various streams which flow into it, one early and important task is the need to thoroughly inspect the bridges on the route to ensure they are in good condition and structurally sound to carry the new railway.
At five underbridges – structures which sit under the railway - along the route, we have carried out inspections and a programme of work is now underway to bring them up to scratch.
Each structure will be grit-blasted to remove the old paint from the bridge and take it back to the base metal. Corroded sections of the bridge will be replaced and repairs carried out where needed. New timber bridge decks will be installed to strengthen and support what will soon be a double-tracked railway running over them.
The bridge will then be repainted using a special paint system that will ensure it is water-proofed and coated to protect it for 25 years.
To create the right conditions to carry out this work we will build a fully encapsulated access scaffold. This is a scaffold that surrounds the bridge on all sides - including underneath - and is fully covered and sealed.
The encapsulation protects the work from the impact of weather but more importantly is a crucial environmental protection – stopping the old toxic lead paint from leaking out into the environment. Carrying out the work in a sealed environment means that the toxic spoil can be removed in a controlled way and disposed of appropriately.
Sean Clemie, Senior Project Manager for the structures work on the route said: "In the same way as the old track bed is being dug out and replaced to bring it up to modern standards, the same principle applies with the underbridges on the route.
"Taking them back to their base metal lets us see clearly what we need to do to repair and replace any damaged or corroded steel sections, as well as strengthening the timber bridge decks.
"Once we have carried out the structural repairs, we can then apply the specialist paint system that lasts for 25 years and ensures the bridges are coated and protected against the impact of weather and corrosion – something which is particularly important in a coastal location
"So, if you were wondering what was happening under the big white tents that will spring up between now and August on bridges along the route, now you know."
Construction News
29/03/2022
Levenmouth Rail Link: 'Various Elements Of Work' Underway


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip