Network Rail has welcomed the progress being made to reinstate the Levenmouth Rail link, with "various elements of work springing up across the route".
Network Rail said that with the proximity of the river and various streams which flow into it, one early and important task is the need to thoroughly inspect the bridges on the route to ensure they are in good condition and structurally sound to carry the new railway.
At five underbridges – structures which sit under the railway - along the route, we have carried out inspections and a programme of work is now underway to bring them up to scratch.
Each structure will be grit-blasted to remove the old paint from the bridge and take it back to the base metal. Corroded sections of the bridge will be replaced and repairs carried out where needed. New timber bridge decks will be installed to strengthen and support what will soon be a double-tracked railway running over them.
The bridge will then be repainted using a special paint system that will ensure it is water-proofed and coated to protect it for 25 years.
To create the right conditions to carry out this work we will build a fully encapsulated access scaffold. This is a scaffold that surrounds the bridge on all sides - including underneath - and is fully covered and sealed.
The encapsulation protects the work from the impact of weather but more importantly is a crucial environmental protection – stopping the old toxic lead paint from leaking out into the environment. Carrying out the work in a sealed environment means that the toxic spoil can be removed in a controlled way and disposed of appropriately.
Sean Clemie, Senior Project Manager for the structures work on the route said: "In the same way as the old track bed is being dug out and replaced to bring it up to modern standards, the same principle applies with the underbridges on the route.
"Taking them back to their base metal lets us see clearly what we need to do to repair and replace any damaged or corroded steel sections, as well as strengthening the timber bridge decks.
"Once we have carried out the structural repairs, we can then apply the specialist paint system that lasts for 25 years and ensures the bridges are coated and protected against the impact of weather and corrosion – something which is particularly important in a coastal location
"So, if you were wondering what was happening under the big white tents that will spring up between now and August on bridges along the route, now you know."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...