2021 Affordable Housing Programme Successfully Complete

Construction News Image
Comhairle nan Eilean Siar has welcomed the successful completion of the 2021 Affordable Housing Programme finished 2021 with the official opening for Lady Matheson Court in Stornoway (6 homes), in December, and started the new year with the handover of James Place in Tarbert (8 homes), in January.

The year-to-date total handover is 78 homes, including the following which has been completed since October 2021:

• Sinclair Avenue, Stornoway – 16 homes for rent – completed in stages between 14 October 2021 and 24 January 2022

• Sinclair Avenue, Stornoway – 6 shared equity homes – completed 14 October 2021

• Ionad Mairi Bremner, Howmore, South Uist – 4 homes for rent – completed 10 January 2022

• James Place, Tarbert – 8 homes for rent – completed 17 January 2022

The developments below are either underway or at various land stages:

• Gleann Mor, Barvas – 8 homes for rent – on site

• Johnstone Court, Balivanich – 10 homes for rent – on site

• Bremner Court, Goathill – 50 Housing with Extra Care – on site

• Goathill – 2 shared equity homes – on site

• Goathill – 22 homes for rent – on site

• Rathad na Ceardaich, Barra – 6 homes for rent – on site

• Lochmaddy – 8 homes for rent – awaiting land transaction

• Blackwater Phase 1 – 72 homes for rent – resumption concluded, awaiting land transaction
-- Advertisement --
NorthernAsbestosServicesLtd



• Crowlista – 4 homes for rent – awaiting resumption

The Howmore development and the Housing with Extra Care element of the Goathill project have both been named in memory of Mairi Bremner – Ionad Mairi Bremner and Bremner Court respectively. Mairi, from South Uist, was a hugely respected community champion, who represented the Iochdar ward as its Councillor from 1979 to 2003. In addition to many other public positions throughout the years, Mairi also served on the Board of Hebridean Housing Partnership from 2009 until her passing in September 2019. It is testament to how highly regarded Mairi was throughout the islands that there is more than one development named to honour her life in public service, her compassion, her kindness and her humour. We remember Mairi with fondness.

Cllr. Kenny John MacLeod, Chair of the Communities and Housing Committee, said: "The Comhairle is pleased to see the programme progressing well, with 78 homes handed over since April 2021, and works continuing in particularly challenging circumstances. We are also very pleased to see the progress of developments in both South Uist and Lewis bearing the name of our former colleague and friend, Mairi Bremner. Given her work in housing and social issues over the years, we believe Ionad Mairi Bremner and Bremner Court will be a lasting tribute to her legacy. We thank all Scottish Government and HHP for ongoing partnership work on the Affordable Housing Programme."

The Comhairle has commenced work on the next Housing Needs and Demands Assessment (HNDA) to contribute to the evidence base for the number and type of homes we need in the Outer Hebrides. We hope to finish this piece of work over the summer, and it will then feed into the next Local Housing Strategy and Local Development Plan.

Iain MacMillan, HHP Chair, commented: "HHP is delighted that we continue to provide new affordable homes right across the islands. The 78 new homes already made available since April 2021, the 98 new homes currently underway, and the 84 new homes awaiting a start once land transactions are completed, reflect a strong and ambitious development programme which we are progressing in partnership with Scottish Government, Comhairle Nan Eilean Siar and our contractors. To enable development to continue we need clear evidence of demand for rented housing and that if people want to rent a property that they make an application to HHP for housing. Future investment is dependent on having a clear demand from current and future tenants."



Latest Construction News

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment. The pane
15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire. The event will take place on Monday, 28 April, from 4 pm t
15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle. This key appointment will enable crucial work to progress on the project, including feasibility s
15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027. The £5 million
15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment. The practical guide is designed for landowners, developers,
15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it
14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year. The initial grant of £78.687 million from the Scottish Government
14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure. From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont
RBT Underfloor LimitedMorris & Spottiswood LtdMulberry Kitchen DesignScaftec LtdTALA TrainingK & I Paterson LtdForde Training Services LtdPlant Glazing LtdThe Water PointCRGP Limited