22/03/2022

Construction Milestone On Major Power Line Development

Construction News Image
SSEN Transmission has reached a major construction milestone in its ongoing works on a multi-million-pound power line development in Scotland.

The work, which saw the first towers installed in the new development between Port Ann to Crossaig, is part of SSE's £12.5bn Net Zero Acceleration Programme.

The first two of 149 steel towers have been installed for the replacement overhead line which will span across 45km between Lochgilphead and Crossaig Substation. Teams have also made great progress with the installation of 48km of access track and 21 of the tower foundations as part of the ongoing project.

The project is the second phase in the wider Inveraray to Crossaig powerline upgrade, with the first phase – Inveraray to Port Ann – energised in July 2021.

The new power line will replace the existing infrastructure in the area, which was originally built in the 1950s and is now reaching the end of its operating life. The new replacement power line will provide a new robust and reliable transmission network across the region and will serve as one of the transmission network's main arteries in the west of Scotland. It is one of the most significant electricity network investment in the region in decades.

-- Advertisement --
NorthernAsbestosServicesLtd

Once complete, the powerline will operate at 132kV with the capacity to be upgraded to 275kV in the future, forming a key part of SSEN Transmission's Argyll 275kV strategy. This will see the electricity transmission network in the region reinforced to enable the connection of over 600 MW of new renewable generation, playing a key role in the transition to net zero emissions and the fight against the climate emergency.

David Auld, Project Manager for SSEN Transmission, said: "This is a major milestone in our ongoing project between Port Ann and Crossaig, and I'm delighted to see the first of 149 towers installed as part of this highly complex engineering project."

David continued: "This is the second phase of the major Inveraray to Crossaig overhead line reinforcement project, and once complete, it will not only provide a more resilience transmission network in Argyll, but also provide increased capacity to allow more renewable electricity generation to be connected to the grid – allowing clean energy to be transported to where it is needed most and assist in the fight against the climate emergency.

"As a stakeholder-led business we've been working closely with the local community and stakeholders to share information with them about the project and to help mitigate the impacts of our activities, and we thank them for their continued patience and understanding as we deliver this critical national infrastructure which will serve the region for many decades to come."

Latest Construction News

26/11/2024

Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024

The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024

First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024

A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024

Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024

The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024

West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024

Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024

Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024

Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...
RBT Underfloor LimitedMorris & Spottiswood LtdMorris & Spottiswood LtdCharlie Cowie LTDBabbity EnvironmentalJRF Chimney Specialists and Heating DistributorsKattrak International LtdEco SIPs Homes LimitedRethync LtdE & P Bricklaying
Terms and Conditions
2024/11/27 01:17:50