Scotland's electricity transmission owner, SSEN Transmission, has submitted to the energy regulator, Ofgem, robust proposals to reinforce the Argyll transmission network from 132kV to 275kV operation.
At an estimated cost of around £400m, this investment is being taken forward as part of the SSE Group's Net Zero Acceleration Programme, which will see £12.5bn invested in the five years to 2026, or £7m every day. SSEN Transmission alone expects to invest around £4bn over this period as it delivers a network for net zero emissions.
The Argyll 275kV strategy is required to support the connection of several new renewable electricity generation schemes across Argyll and to transport that power to areas of demand across Scotland and beyond. It will support the connection of at least 560MW of new renewable electricity generation, enough to power more than 500,000 homes.
The Argyll 275kV strategy consists of the following five main components:
• A new substation at Creag Dhubh connecting to SP Transmission's existing Dalmally-Windyhill transmission line via around 14km of new overhead transmission circuits;
• Around 10km of new overhead transmission circuits connecting Creag Dhubh substation to the existing Inveraray-Crossaig circuits;
• The replacement of existing substations at An Suidhe and Crarae along the route of the Inveraray-Crossaig line;
• Establishing a new substation at Craig Murrail and relocation of the Port Ann Grid Supply Point to this site; and
• Establishing a new substation in the vicinity of the existing Crossaig substation.
Rob McDonald, Managing Director of SSEN Transmission, said: "Submission of our Initial Needs Case for the Argyll 275kV strategy marks another key milestone in delivering a network for net zero emissions.
"With the existing network in Argyll close to capacity, the project is essential to increase the operational capacity of the Argyll transmission network, supporting the connection of new renewable electricity generation in the area and to transport that power to areas of demand."
Rob continued: "We now look forward to working constructively with Ofgem and our stakeholders to unlock the investment required in a timely manner. This investment will create hundreds of skilled jobs throughout the supply chain as well as boosting local and national economies, supporting a green recovery from the coronavirus pandemic."
In parallel with the regulatory approvals process SSEN Transmission continues to progress the detailed designs for the various components of the Argyll 275kV strategy. Following significant stakeholder engagement, which has led to several changes to SSEN Transmission's proposals, planning applications are due to be submitted in the coming months to Argyll and Bute Council for all substation works; and to the Scottish Government for all overhead transmission line works.
Subject to necessary regulatory and planning approvals, SSEN Transmission expects construction to be underway in 2024 with the scheme fully energised in April 2027.
Construction News
15/03/2022
SSEN Proposes Argyll Transmission Network Improvements


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip