Transport Minister Jenny Gilruth has met with the A83 Task Force to discuss the wide range of work to identify a solution to the challenges at the Rest and Be Thankful.
On the design process, five consultants have now been invited to tender for the next stage of the work to design a long-term solution with five options currently under consideration for the preferred route at Glen Croe. They are, in no particular order, Arcadis Consulting (UK) Limited / Sweco UK Limited; Ove Arup & Fairhurst; Atkins Limited / WSP UK Limited; Stantec UK Ltd / RPS Consulting Services Limited and Jacobs / Aecom.
In recognition of the disruptive closures at the Rest and Be Thankful, plans are being progressed for a medium term resilient route through Glen Croe, with finalised proposals expected this Autumn.
To help inform the design work, discussions have been held with the Norwegian Government to learn lessons from their wide experience of constructing tunnels. Norway's roads network contains many tunnels due to the landscape of the country, which is similar to that found at the Rest and Be Thankful. As such Transport Scotland has been keen to learn about Norway's processes and methods for developing and constructing tunnelling projects.
Transport Minister Jenny Gilruth said: "Improving the resilience of the A83 at the Rest and Be Thankful remains a key transport priority for the Scottish Government. So I am keen to meet the A83 Task Force to listen to and understand more about their views on our plans.
"I want to assure local residents, business and communities that we are aware of the urgent need to make progress on this – that is why we are pursuing measures to maintain connectivity on a short, medium and long term basis in parallel.
"Identifying the preferred route corridor for a resilient long term solution last year was a major step forward for this vital work. With the shortlisting of five design consultants, we hope to appoint the best candidate to take forward that work as soon as due process allows. But other work will continue in the meantime.
"We intend to finalise proposals for the medium term solution for the resilient route through Glen Croe by the Autumn. Ground investigations are now underway to help inform the design work for both the medium and long term options.
"As two of the five options for the long term solution include a tunnel, we have held discussions with the Norwegian Government to learn from their experiences in assessing and building tunnels. As the project progresses, we will continue to learn from Norway's experience, and that of other relevant communities and countries as we work towards finding the right solution to meet the need to create a truly resilient and safe route for the A83."
Construction News
04/03/2022
Transport Minister Updated On Rest and Be Thankful


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont