SSEN Transmission has submitted a Section 37 planning application to the Scottish Government for the 132kV electricity transmission network overhead line infrastructure that will connect Shetland to the GB energy system.
Two 22km circuits, which will be a combination of overhead line and underground cabling, will provide a connection between the proposed Gremista GSP and Kergord substation, which is currently in construction as part of the Shetland HVDC link. Upon completion, this will provide a connection to Shetland's local electricity distribution network, connecting the islands to the GB energy system for the first time, helping secure Shetland's future security of supply.
The Kergord-Gremista connection follows extensive local consultation which has helped shape the project's design.
At the Kergord end of the two circuits, the 132kV infrastructure will be undergrounded for around 5.8km, with another 900m section of one of the circuits to be undergrounded at Sweenister. As the transmission circuits approach and connect to Gremista GSP, the two circuits will be undergrounded covering a distance of 4.1km in total.
SSEN Transmission has also committed to underground around 11km of existing 33kV electricity distribution overhead network infrastructure running in parallel with the proposed 132kV overhead lines and 500m of existing electricity 11kV distribution overhead network infrastructure, reducing the cumulative visual impact of overhead network infrastructure on Shetland's landscape.
In total, around half of the proposed 132kV connection is to be undergrounded which when coupled with the undergrounding of existing electricity distribution infrastructure, strikes a balance between minimising visual impacts on Shetland's landscape; mitigating potential environmental impacts, particularly on protected species of birds; and protecting electricity consumers from the high costs associated with undergrounding.
Submission of the Kergord-Gremista 132kV connection Section 37 planning application follows last year's planning submission to Shetland Islands Council for Gremista GSP.
The proposed site, which has been identified as a suitable area for development in Shetland Island Council's Local Development Plan, has been carefully selected due to its close proximity to the existing industrial infrastructure in the Black Hill Industrial Estate, with the GSP proportionate to existing buildings; and where the GSP will connect to Shetland's existing electricity distribution network.
Separately, SSEN Transmission recently submitted a funding request to the GB energy regulator, Ofgem, under Ofgem's Medium Sized Investment Project (MSIP) Uncertainty Mechanism, for the allowance required for both the Kergord-Gremista 132kV connection and Gremista GSP.
Grant Smith, Lead Project Manager, said: "The submission of our Section 37 planning application for the Kergord to Gremista 132kV transmission circuit which follows last year's planning application for Gremista Grid Supply Point, alongside our recent funding request to Ofgem, marks a major milestone in helping secure Shetland's future security of supply.
"Upon completion, these projects will connect Shetland to the GB energy system for the first time and will enable the supply of clean power to homes and businesses, even at times when local generation on Shetland's electricity distribution network does not meet demand.
"Our proposals have been carefully developed to minimise the impact on Shetland homes, businesses and the local landscape as we have sought to balance a range of economic, environmental and technical factors.
"We look forward to the outcome of our planning applications and remain committed to working closely with Shetland Islands Council, the local community and wider stakeholders to deliver this critical infrastructure to support Shetland's future energy needs."
Construction News
03/03/2022
SSEN Transmission Submits Section 37 Planning Application


22/04/2025
Scottish Renewables has urged the Scottish Government to adopt a tailored approach to community benefits from renewable energy developments to ensure they deliver a lasting strategic legacy for local areas.
Responding to a public consultation on the issue, the industry body advocated for flexibilit

22/04/2025
Construction is scheduled to commence this month, on Monday, 28 April, on a new £4.1 million housing and office development in Stranraer by social landlord Wheatley Homes.
The project at Ashwood Drive will see the creation of nine two-bedroom homes available for social rent. The housing block will

22/04/2025
Two marine companies based in Norfolk have secured multi-million pound vessel charter agreements with ScottishPower Renewables, playing a key role in the development of the East Anglia THREE offshore windfarm.
NR Marine Services, based in Caister, and OEG, located in Great Yarmouth, will provide ve

22/04/2025
A significant advancement in the energy transition has been achieved with the successful demonstration of a world-first technology that allows High Voltage Direct Current (HVDC) transmission systems from different manufacturers to connect and operate seamlessly, boosting network reliability.
SSEN T

22/04/2025
Homeowners and community groups across the Scottish Hydro Electric licence area can access funding support for new electricity connections, courtesy of the Scottish Hydro Electric Community Trust.
Established in 1998 by Scottish Hydro Electric plc (now SSE plc), the independent charitable trust is

22/04/2025
Homes for Scotland (HFS), the representative body for the majority of new home builders across all tenures, has announced a partnership with VELUX to bolster the operating environment for small and medium-sized enterprise (SME) home builders.
The collaboration seeks to support the growth and susta

22/04/2025
A significant proportion of Scots believe that achieving net zero emissions by 2045 will lead to an improvement in their quality of life, according to newly published official figures. The Scottish Climate Survey revealed that 44% of respondents anticipate a positive impact from the transition, comp

22/04/2025
Ayrshire-based McTaggart Construction has paid tribute to the exceptional long service of six key employees, each marking their 25th year with the company during 2025.
The award-winning specialist affordable home builder acknowledged the significant contributions of these individuals, who have play

22/04/2025
With just one month remaining until the scheduled reopening on 18 May, significant progress has been made on the East Kilbride-Glasgow Central line upgrade, as engineers have successfully laid new tracks and installed overhead power lines along the route.
The 16-week closure, implemented in January

22/04/2025
Construction has commenced on Midlothian Council's newest energy-efficient housing development, located on the former Danderhall library and leisure centre site. Contractor Ogilvie Construction has begun work on the £6.93 million project, which will provide 23 one-and two-bedroom flats across two bl