Network Rail has announced a £32m programme of improvement works for Glasgow's Argyle line.
Customers are being urged to plan ahead as the line will be closed between Rutherglen and Exhibition Centre from March 13 to May 8.
During the closure, engineers will complete a series of projects to repair and replace tracks, tunnels and bridges on the line through Glasgow city centre.
Work to modernise Anderston station and install a new lift shaft will also begin, with upgrades to the booking office, concourse and platform stairs taking place.
Many services, which would normally operate via Glasgow Central Low Level, will be diverted into Glasgow Central High Level or Glasgow Queen Street Low Level. Revised services will operate on all routes during the closure, and journey times may be extended on some services to allow for trains taking a diverted route.
During the works, replacement bus services will be running from Carmyle, Newton, Cambuslang, Rutherglen, Dalmarnock, Bridgeton, Glasgow Central, Exhibition Centre, and Partick.
Alan Ross, Network Rail Scotland's director of engineering and asset management, said: "This major investment in our railway infrastructure is designed to keep the line operating reliably for our customers.
"While we appreciate that some journeys will be impacted during the line closure, our work will mean that disruption and delays will be less likely in the future. And at Anderston, starting work on a new lift will make the station more easily accessible in the future.
"Such a large programme of engineering work cannot be completed without closing the line, but our teams will be working hard to finish this project as quickly as possible.
"We're urging passengers to plan ahead when travelling during our works, whether they're commuting to or from work, travelling to watch football or attending an event at the Scottish Event Campus (SEC).
"We'd like to thank all passengers and lineside neighbours for their patience and understanding while we carry out this essential work."
David Simpson, ScotRail operations director, said: "The enhancements to the track and tunnels will improve punctuality and reliability on the route for years to come.
"Journeys will be impacted during the line closure, but once this essential work is carried out, disruption and delays will be less likely in the future.
"It's all part of our ongoing commitment to deliver a modern, reliable, efficient, green and clean rail network as we move forward."
Rail replacement services at affected stations will run every 30 minutes on Monday to Saturday and every hour on Sundays.
Services from Lanark, Shotts and Motherwell to Cumbernauld will operate as normal with half the normal service levels at other stations on the Argyle line outside of the closure zone.
Construction News
28/02/2022
Network Rail Announces £32m Improvement Works


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont