Network Rail has welcomed the progress in the construction of the new Inverness Airport station.
Work got underway on the new £14m station in October and early activity has seen the site set up, groundworks and the creation of embankments at the location adjacent to the airport.
The project will deliver a two-platform station on the Aberdeen-Inverness line with step-free access, via a footbridge with lifts. Work also includes the creation of a passing-loop (a second line of track through the station) and the closure of Petty Level crossing.
The station will have 64 car parking spaces with 10 electric charging facilities, four disabled spaces and cycle parking. There will be a new access road to the station for motorists and access to both platforms for pedestrians and cyclists.
Main construction work on the new platforms, including the concrete lift shafts and footbridge foundations will begin in the new year. It will also include the creation of access roads and carpark.
The new station will deliver improved travel links to the growing Inverness Airport Business Park and the new town of Tornagrain.
The development also comes with the advantage of closing the level crossing at Petty which will improve the safety of the line and the operation of the new station, which is due for completion in December 2022.
David Millar, Project Manager for Network Rail, said: "(This) year promises to be an exciting and busy one for this project. On completion the new station will enhance the local area and improve connectivity for nearby residents and the wider Inverness area by providing a new sustainable transport interchange.
"Getting on-site to start the build is a significant milestone in the project and we have made good early progress.
"We will continue to work with our partners to deliver this new station as quickly as possible for our customers and the wider community."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...