Network Rail Replaces Bridge Over Railway At Lynebeg

Construction News Image
Network Rail has demolished and replaced the bridge over the railway at Lynebeg, south of Inverness on the Highland Mainline between Perth and Inverness.

It is part of supporting work ahead of the dualling of the A9 between Tomatin and Moy.

In continuous working across 78 hours from Friday night until Tuesday morning, the 1884 Victorian masonry structure was demolished and replaced with 660-ton twin-track concrete box structure.

The construction team used a Self-Propelled Modular Transporter (SPMT) system to carry the structure from the site compound, where it was constructed offline over a 10-week period, before manoeuvring the massive 660-ton structure several hundred meters along the B1954 and sliding it to its final position.

Two 750-ton cranes then lifted seven concrete wingwalls, which were also constructed on site, into position. Before the railway was fully reinstated and checked ahead of re-opening to traffic early on Tuesday morning (30 November).

-- Advertisement --
NorthernAsbestosServicesLtd

The new bridge will strengthen, safeguard, and futureproof the route for the long-term including dealing with the weight and volume of traffic which passes over it on a daily basis and accommodating any future double-tracking of the line should that be proposed in the future.

During the same 78 hour possession, a 1200x800mm pre-cast box culvert and a 900mm twin wall plastic culvert under the track, at two locations to accommodate the forthcoming A9 works.

Billy McKay, Network Rail's Programme Manager for the Lynebeg bridge replacement works, said: "We are delighted that the work to replace the bridge at Lynebeg was completed successfully and the railway re-opened to traffic as planned – despite terrible weather conditions and the impact of Storm Arwen.

"The installation was complex due to requirement to remove the existing railway infrastructure including cabling, track and the embankment, before the concrete bridge could be pushed into its final position. And all against the clock due to the need to reinstate and re-open the line to traffic at the end of the possession.

"As well as upgrading the railway bridge, the team is delighted to have played a part in supporting the future dualling of the A9."

Works will continue on site for several weeks to complete the new structure, including cladding the concrete wing walls with the recovered stone from the original stone arch bridge which was constructed as part of the Highland Mainline in 1884.

Latest Construction News

26/11/2024

Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024

The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024

First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024

A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024

Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024

The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024

West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024

Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024

Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024

Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...
Morris & Spottiswood LtdRBT Underfloor LimitedToner Damp Proofing SuppliesNo HydroSEEIT3DCF Concrete PumpingMaccaferri LtdDiscount Kitchens and Bathrooms LtdShopfronts ScotlandJSJ Foam Insulation Ltd
Terms and Conditions
2024/11/27 01:19:06