SSEN Transmission has awarded Balfour Beatty an £85 million contract to deliver the second phase of overhead line works in the West of Scotland between Port Ann and Crossaig.
Phase Two of the scheme will see Balfour Beatty design, construct and engineer a new 45km 275kV double circuit overhead line between the existing substations at Port Ann and Crossaig. Once operational the new power line will reinforce the network in the region and facilitate the connection of new renewable energy to the grid, playing a key role in the UK's transition to net zero emissions.
The award follows the successful energisation of the first phase of the project, which saw Balfour Beatty install 37km of 275kV double circuit line from Inveraray to Port Ann.
The team will use Building Information Modelling (BIM) software and drones to plan and design the line reducing safety risks, while improving both the quality and efficiency of works.
Ian Currie, Managing Director of Balfour Beatty's Power Transmission and Distribution business said: "At Balfour Beatty, sustainability is at the heart of what we do - we want to build a better, greener future.
"Through our long-standing relationship with SSEN Transmission, we will continue to utilise our expert capability to help provide the necessary upgrades to the Argyll area and beyond."
Keith Inglis, Project Director of SSEN Transmission said: "This is great news for Balfour Beatty, SSEN Transmission, and of course those relying upon the Transmission Network in the Argyll peninsula.
"The award of this next phase to Balfour Beatty builds upon the success in phase 1 but also numerous other projects we have collaborated on in the past 10 years."
Phase Two enabling works have already commenced, with completion of the whole project expected in 2023. At peak construction, the scheme will employ a workforce of approximately 300 people, as well as providing a number of apprenticeship opportunities.
Construction News
28/09/2021
Balfour Beatty Awarded £85m West Of Scotland Contract


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont