Construction News

24/09/2021

Construction Continues On New NESS Energy From Waste Facility

Construction News Image
Aberdeen City Council has welcomed progress on the construction of a the new NESS Energy from Waste Facility, with the site expected to create energy from non-recyclable waste by Spring next year with the facility fully operational by the end of that year.

The Council's capital programme committee agreed an update which told the large majority of engineering and design work is now successfully concluded and procurement of sub-contractors to undertake the construction, manufacture and installation of plant components is also nearly complete.

The Ness Energy Project Residual Waste Treatment plant is being build by Aberdeen City Council, Aberdeenshire Council, and Moray Council to dispose of non-recyclable waste by creating energy, and the main contractor is Acciona Industrial and Acciona Servicios Urbanos.

Aberdeen City Council capital programme committee convener Councillor Marie Boulton said: "The progress at the site is great and it is good to hear the facility is on target to start commissioning and be fully functional next year.

"We look forward to hearing more updates at committee."

A report to committee said the large majority of engineering and design work is now successfully concluded and procurement of sub-contractors to undertake the construction, manufacture and installation of plant components is also nearly complete.
-- Advertisement --
NorthernAsbestosServicesLtd



Manufacture of many components of the boiler, turbine, generator and flue gas treatment systems is now largely complete with these items either installed or in storage in Aberdeen ready for installation. To date, the contractor has not reported any significant supply chain issues that will affect the works programme.

Progress on site has continued broadly in line with the revised programme with the formation of the waste bunker super- and substructure is now complete. Installation of the steel structure for the waste reception hall on the northern boundary of the site is now underway. The erection of the steel framework for the boiler is close to completion and installation of the boiler is well advanced. The turbine and generator set are now installed with the building steelwork also complete.

The report said significant progress has been made on the installation of the Flue Gas Treatment system and the 80m stack was erected in June 2021.

Many other peripheral activities have also been commenced such as installation of the air-cooled condensers and foundations for electrical buildings, weighbridges and fire control systems.

The report said the cyber-attack suffered by SEPA in December 2020 continues to severely hamper its ability to manage Permit applications. In recent months, progress has been made and the contractor reports that most issues relating to the PPC Permit application have been resolved with SEPA and a draft permit is imminent. SEPA will undertake a public consultation on the application before determining the outcome. The delay in finalising the Permit is not currently considered to be a significant risk to delivery of the project in line with the approved programme, the report said.

Since the March committee meeting, the Contractor has maintained operations at the site by following additional COVID-19 related working practices in line with government and other relevant guidance. There has been minimal impact on project delivery albeit that a small number of positive COVID-19 tests in sub-contractor teams has resulted in staff self-isolating in line with COVID-19 regulations. In addition, other staff members have been required to self-isolate following contact from Test and Protect. To date, all staff have returned to work.

The report said current indications are that commissioning is anticipated to commence as planned in Spring 2022 with the facility fully operational by the end of 2022.

Latest Construction News

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment. The pane
15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire. The event will take place on Monday, 28 April, from 4 pm t
15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle. This key appointment will enable crucial work to progress on the project, including feasibility s
15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027. The £5 million
15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment. The practical guide is designed for landowners, developers,
15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it
14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year. The initial grant of £78.687 million from the Scottish Government
14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure. From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont
Morris & Spottiswood LtdRBT Underfloor LimitedJohnston Oils LimitedHodge Plant LimitedNorth West Lifting SpecialistsEuro-Fab (Scotland)James Macqueen Building Contractors LtdInverness Core Drilling LtdJRF Chimney Specialists and Heating DistributorsJGas