Scottish Water have unveiled an interactive virtual platform to highlight a £3 million improvement project to upgrade the water network in Bowmore, Islay.
Work is due to get underway on Monday 11 October 2021, to replace almost four miles of water main on many streets across the town to help prevent bursts on the network.
Now, customers and visitors planning to travel to the island, home to the famous Bowmore distillery since 1779, can access information about the project via the Bowmore Water Mains Improvement Project, including meeting the project team, video fly-throughs to show the scope of the work and to ask any questions about the work.
This vital project, to replace ageing infrastructure, will be delivered in phases by local contractors McFadyens Contractors (Campbeltown) Ltd and is expected to take around 18 months to complete.
Traffic management, which may include temporary traffic lights, will be in place as required as the works progress across the town. All traffic management has been agreed in liaison with Argyll & Bute Council.
Georgina Reid, Scottish Water's corporate affairs manager for the west, said: "Some of the water mains serving our customers in Bowmore are over 100 years old now and there were a number of bursts on the network.
"This major upgrade work is vital to add resilience to the water network for the future and help reduce the chance of pipes bursting.
"We would like to thank our customers and visitors to Islay for their patience while we deliver this important water main improvement project."
Construction News
08/09/2021
Major Water Network Improvement Project Announced For Islay


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont