Work Continues On New Helensburgh State-Of-The Art Leisure Centre

Construction News Image
Argyll and Bute Council has welcomed the progress being made in the development of Helensburgh's state-of-the art leisure centre, despite the construction challenges brought by the global pandemic.

One year after construction began, the main building is structurally complete, with the external Lomond stone blockwork and glazing installed, and new flood defences for the town and landscaping is well underway.

When it's complete the council's £22 million development will provide residents and visitors with new swimming and studio pools, and a gym and café with stunning views of the Clyde.

The Helensburgh Waterfront Development is designed to be fully accessible for all users and includes:

• Pool pod access facilities to enable wheelchair users and anyone with mobility issues to independently access the pool.

• A moveable floor in the studio pool, making it easier for all swimming abilities

• A Changing places toilet with hoist equipment and a changing bench.

As the local economy starts to recover from the impact of the pandemic, the build continues to support local employment. There are over eighty people working on site and many local contractors working on the project.
-- Advertisement --
NorthernAsbestosServicesLtd



The project is creating vital training and experience for people starting out with their careers. The Council and its construction contractor Heron Bros Ltd offer a number of work placements and ongoing learning including:

• Apprentice civil engineers and stonemasons

• Trainee quantity surveyors

• Civil engineering graduates

• Apprentice joiners, plumbers and electricians.

Councillor Gary Mulvaney. Policy Lead, Financial Services and Major Projects, said: "This development not only offers a first class facility for residents and visitors, it provides vital skills and training to the next generation, and support for the local economy now when it needs it.

"With ongoing Covid restrictions, it has taken a huge team effort from the Council, Heron Bros and our internal and external design consultants to get us to this important milestone.

"It is remarkable to think of the progress to date considering the back office staff behind the Waterfront Development are working remotely to deliver the project.

"The progress achieved in the face of considerable challenge is a testament to the power of partnership and professionalism. Congratulations to everyone involved."

Cathal Heron, Regional Director for the Main Contractor, Heron Bros, added: "Heron Bros is extremely pleased with the progress made to date as we mark such a key milestone for the project. The celebration represents a high point not only for the project build, but for the entire project team, who have worked so effectively together in making such impressive progress."

The project is supporting a number of community projects with donations from Heron Bros to local charities and material supplied to help initiatives including the Helensburgh Community Centre.

The Council appointed contractors Heron Bros Ltd to start work in August 2020. The project represents investment in Helensburgh of more than £22.3 million. This includes £5million awarded from the UK Government Libor Fund and £100,000 from SportScotland.

Latest Construction News

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment. The pane
15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire. The event will take place on Monday, 28 April, from 4 pm t
15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle. This key appointment will enable crucial work to progress on the project, including feasibility s
15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027. The £5 million
15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment. The practical guide is designed for landowners, developers,
15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it
14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year. The initial grant of £78.687 million from the Scottish Government
14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure. From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont
RBT Underfloor LimitedMorris & Spottiswood LtdAbout Grab Hire Uk LimitedNational Access & Scaffolding Confederation (NASC) - ScotlandAC Cable Solutions24-7 HealthcareThe Scottish Natural Insulation HubMaccaferri LtdPD ServicesMV Commercial