BEAR Scotland are set to begin work on £2.35 million surfacing improvements on the A90 near Stonehaven.
The project is planned to take place over four weeks using 24-hour working with all improvements expected to be completed by 6.30am Monday 06 September, subject to weather conditions. To ensure roadworkers as well as motorists are kept safe throughout the project, restrictions will be in place on the A90 for safety as follows:
• Thursday 05 and Friday 06 August – Lane closures on both the northbound and southbound carriageway will be in place from 7.30pm on Thursday night until 7.30pm on Saturday night to allow for contraflow traffic management to be installed ahead of the project.
• Saturday 07 August to Monday 06 September – To ensure the safety of roadworkers and motorists, a contraflow system will be in place starting after the Drumlithie Junction and ending before the A92 Interchange from 6.30am Saturday 07 August until 6.30am Monday 06 September. Within the scheme extents the Temple of Fiddes and Auquhirie Junctions will be closed with signed diversion routes in place to guide motorists to their destination. Residents within the site extents will be escorted through the worksite when safe to do so.
Consultation has taken place with all relevant stakeholders in advance of the resurfacing improvements to make them aware of the traffic management arrangements.
Strict physical distancing protocols, in line with Scottish Government guidance, will be in place to ensure all site personnel remain safe once the project gets underway.
Commenting on the improvements, Ian Stewart, BEAR Scotland's North East Representative, said: "This £2.35 Million investment from Transport Scotland will greatly improve and strengthen this section of the A90 near Stonehaven, as well as create a smoother and safer journey for motorists.
"Due to the scale and nature of the works we need to use a contraflow system for the safety of our teams and the travelling public. To limit disruption as much as we can, teams will be working around the clock to complete the project as quickly as possible.
"We thank motorists for their patience in advance while our teams carry out these essential improvements on the A90. We encourage road users to plan their journeys in advance by checking the Traffic Scotland website for up to date traffic information and allow some extra time to reach their destination."
Construction News
04/08/2021
£2.35m A90 Resurfacing Scheme To Get Underway


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip