Transport Scotland's operating company, BEAR Scotland, is set to resurface 0.8 kilometres of the M9 northbound main carriageway prior to Junction 1A and 0.5 kilometres of the M9 northbound Junction 1A off-slip during four overnight closures commencing on Thursday 29 July.
On the nights of 29 and 30 July, the M9 northbound will be closed between Junction 1 and Junction 1A from 20:30 until 06:00. A diversion route for northbound traffic will be signposted via the A8, A902, A90 and A904 to M9 Junction 2, adding approximately 19 minutes and 8.4 miles to affected journeys. Southbound traffic on the M90 will still be able to join the M9 in either direction via Junction 1A.
On the nights of 02 and 03 August, the M9 northbound Junction 1A off-slip will be closed from 20:30 until 06:00. A diversion route for traffic wishing to join the M90 will be signposted via M9 Junction 3, returning on the M9 southbound to exit via the M9 southbound Junction 1A off-slip. This diversion will add approximately 14 minutes and 12.3 miles to affected journeys.
Access for emergency vehicles will be maintained at all times.
Tommy Deans, BEAR Scotland's South East Network Manager, said: "These surfacing improvements will improve the road quality and safety for motorists on this section of the M9.
"Carriageway and slip road closures are essential for the safety of workers and motorists, however we've planned the works to take place overnight to minimise any disruption. We've also planned these works so that we will only be diverting trunk road traffic onto local roads when there is no alternative.
"We will do all we can to complete the project as quickly as possible and thank motorists in advance for their patience."
Consultation has been carried out with emergency services and relevant stakeholders to share information about the project in advance.
Construction News
26/07/2021
M9 Carriageway Resurfacing Works Set To Get Underway


17/04/2025
A joint venture between Sir Robert McAlpine Capital Ventures and Buccleuch Property has successfully acquired 101 Centre Street in Glasgow, signalling a significant investment in the city's burgeoning southbank area. The 50/50 partnership aims to unlock substantial redevelopment potential on the 1.7

17/04/2025
Biotech firm MiAlgae has taken a significant step in its expansion plans by submitting proposals for a new production facility in Grangemouth, Scotland. The move is set to bolster Scotland’s green economic transition, with the first phase of the site projected to generate over 100 green jobs once op

17/04/2025
Scottish Water has completed the initial phase of a significant peatland restoration project at Loch Katrine, a vital source of drinking water for over a million customers in Glasgow and the surrounding areas.
The 400-hectare initiative aims to enhance water quality by reducing the amount of organ

17/04/2025
Clark Contracts has commenced work on a new £30 million purpose-built student accommodation (PBSA) development on Osborne Street in Glasgow.
The contractor was appointed by Ambassador Group to undertake the design and build of the 273-bed project.
Located in the heart of Glasgow City Centre withi

17/04/2025
Seven projects dedicated to promoting, celebrating, and enhancing Scotland's rich and diverse heritage are set to receive a share of £3.9 million in funding. The grants have been awarded through Historic Environment Scotland's (HES) Partnership Fund, which supports third-sector organisations making

17/04/2025
The Viking Community Fund has distributed over £1 million to 52 projects in the Shetland Islands since its inception on 1 September 2024.
The funding has provided vital support to a diverse range of community initiatives, from small grants for youth clubs and sports teams to significant investment

17/04/2025
The Finishes & Interiors Sector (FIS) has announced a new partnership with The Skills Centre to provide essential training and support for individuals seeking careers in the finishes and interiors sector. The collaboration is a direct response to the increasing skills shortage within the constructio

17/04/2025
John Aitchison, Managing Director of Maxi Construction, has announced the successful acquisition of several new contracts. Commenting on the recent awards, Mr Aitchison stated: "These contracts represent repeat business and awards via some of the frameworks we’re appointed to. We look forward to suc

16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan