The Highland Council has welcomed the progress being made on Phase Two of the ongoing Inverness West link works.
Contractors working on the second stage of the Inverness West Link bypass have said they are making good progress.
Road surfacing started on November 5, with access to the canal and roundabout prioritised to allow it to open for the Regatta on 9 and 10 November.
Tow path diversions and temporary car parking for the rowing club were also installed.
The sheet piling to the new wharf began on 10 November using an 80-tonne piling rig with vibrating hammer.
The canal was closed on 18 November to allow the installation of coffer dams at the extents of the bridge and wharf. Pipelines and pumps were also installed for the over-pumping operation.
Constructors are required to keep the canal downstream topped up, which requires 750 litres a second being pumped between the upstream and downstream dams.
The planned works for the next month include:
• Piling of East and West abutments
• Dewatering of the canal
• Concrete tie wall and anchors
• Deep drainage across A82
• Duct installation across the canal
The West Link project has significantly enhanced accessibility since the completion of Phase 1 back in December 2017 and Highland Council is looking forward to all the benefits that Stage 2 will bring for local residents, businesses and visitors to the City of Inverness.
(MH/JG)
Construction News
17/12/2019
Phase Two Of Inverness West Link Works


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont