A new award-winning Lochmaddy Water Treatment Works (WTW) has been officially opened by Na h-Eileanan an Iar MSP Dr Alasdair Allan, with Sgoil Lionacleit Pipe Band.
The WTW is part of a £15 million investment by Scottish Water to provide a single improved water supply for communities across North Uist and Berneray.
The project, which was delivered in partnership with Ross-shire Engineering, recently gained national recognition at the Water Industry Awards 2019 for its use of an innovative construction technique.
The whole plant was built and tested under factory conditions in Muir of Ord before being broken down into 16 modules. These were delivered and re-assembled last year on a site which had been carefully prepared for their arrival by locally-based civil engineering contractor MacInnes Brothers. Lochmaddy is the largest Water Treatment Works that has been built in this way anywhere in the UK to date.
Sgoil Lionacleit Pipe Band kicked off the celebration of the project's completion by piping guests from a new intake that has been built on the shore of Loch Fada to the new WTW above Blathaisbhal.
Dr Alasdair Allan MSP said: "It's great to mark the completion of this important investment for the future water supply that will serve communities across North Uist and Berneray for years to come.
"The project is a great success story for Scottish Water's supply chain here in the Highlands and Islands. From MacInnes Brothers' work on site to Ross-shire Engineering's factory and the specialised transport firms who helped the water treatment works make its 128 mile journey by road and ferry last summer, each part of the delivery process has been critical to the success of the others.
"With the national recognition that has been achieved, it's clear that this approach which was developed for North Uist has potential application much more widely across Scotland and beyond."
Scottish Water Chief Executive Douglas Millican added: "Scottish Water is committed to providing the same high standard of service to our customers for the same low price, no matter where they live in Scotland.
"Achieving that goal for our customers in the islands involves distinctive challenges – and some of those challenges apply just as much to the delivery of complex capital projects. The whole Lochmaddy project team has more than risen to the challenges and the result is plain to see.
"We have a first class new Water Treatment Works which is regarded as an example by others from across the UK and beyond. The construction of the new works has been undertaken well, and with minimal impact on the local community."
(MH/JG)
Construction News
15/08/2019
Award-Winning Water Treatment Works Opened In Lochmaddy


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip