Morrison Construction have successfully installed the 260-tonne steel frame of the Letham Mains Primary School project, marking a key milestone in the €8.6 million development.
The superstructure, including steel work, pre-cast concrete installation and a first-floor reinforced concrete slab, was completed during a 10-week schedule. More than 1,400 components were installed to complete the steel frame.
During the earlier stages of the steel installation, two cranes were utilised to assist the project team with fixing the main sections of the frame.
Morrison Construction Project Director Jim Hanna, said: "It is wonderful to reach this important project milestone. The steel frame has created an outline of the building allowing the community to appreciate how the school will fit into the new development. Now the superstructure has been completed we will progress the ground floor slabs, roofing, cladding and glazing work.
"Our team has enjoyed taking part in community benefit activities including donating to the local foodbank, hosting work experience students, site tours and visiting schools to educate pupils about the industry. We will continue to work closely with the community during construction."
Cabinet member for Education and Children's Services, Councillor Shamin Akhtar, also said: "It's really exciting to see the progress that's being made on our newest primary school. Having the steel frame in place gives a better idea of the size and scale of the building and the facilities that the school will offer for children and their families.
"I'm also pleased to see the amount of engagement that Morrison Construction is undertaking within the local community to ensure the benefits of the project are already being felt."
Letham Mains Primary School, will have a capacity for 500 pupils, with 14 classrooms suitable for pre-school and primary teaching, a dining hall, social space and a two-court PE hall with retractable seating for performance and community use. The external areas will be designed for outdoor learning, PE and play.
The school is being funded entirely by contributions from developers as a requirement for planning approval for 800 new homes at Letham Mains.
Construction is due to be completed in Summer 2020.
(MH/CM)
Construction News
23/07/2019
Morrison Construction Mark Key Milestone In Letham Mains Primary School Project


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont