The last of 84 offshore wind turbines have been commissioned at Beatrice, Scotland's largest offshore wind farm, which has been completed on time and under budget after three years of construction.
Beatrice Offshore Windfarm Limited (BOWL) is a joint venture development led by SSE Renewables (40%), Copenhagen Infrastructure Partners (35%) and Red Rock Power Limited (25%).
The final 7MW Siemens Gamesa turbine was installed in the Outer Moray Firth, around 13km off the coast of Caithness, bringing the site's total installed capacity to 588MW – enough to provide clean, low carbon energy to over 450,000 homes.
Jim Smith, Managing Director of SSE Renewables said: "Completing the offshore construction at Beatrice is a testament to the capabilities of SSE Renewables and our project partners. Delivering one of Scotland's largest ever private investments on time and under budget is a fantastic achievement given its complexity and we would like to thank everyone who has helped us make the project a reality."
Each of Beatrice's 84 turbines, at 188m from sea level to blade tip, stands taller than the London Eye and Beatrice is the largest offshore wind farm in the world to use jacket foundations. These jackets weigh around 1,000 tonnes each and are the deepest water fixed foundations of any wind farm in the world, installed in water depths of over 56m.
As the Beatrice's majority shareholder, SSE Renewables led on the construction process and will manage operations and maintenance from a new base in Wick, having invested over £20m in the coastal town to redevelop the harbour front and renovate two 200-year-old Thomas Telford buildings that will soon become home to up to 90 long-term members of staff.
BOWL engaged constructively to maximise the opportunity for economic benefits and contracts were placed with companies and businesses across the supply chain resulting in a construction spend of over £1.1bn in the UK and around half of this in Scotland. This included CS Wind's Machrihanish factory for turbine towers, Global Energy Group's Nigg Energy Park for marshalling and turbine pre-assembly, Bi-Fab in Fife and on Lewis for jacket foundations and piles, Babcock Marine in Rosyth for the Offshore Transformer Module topsides, JDR Cables in Hartlepool for array cables and Siemens Gamesa in Hull for blade manufacturing.
Christina Grumstrup Sørensen, Senior Partner at Copenhagen Infrastructure Partners stated: "Achieving this final milestone in the construction phase of Beatrice in a safe and timely manner is a result of the excellent performance of the project team and the good cooperation with competent suppliers. We are very pleased to see all 84 turbines feeding green, renewable electricity into the grid. This is a major milestone in our offshore wind strategy, where we are developing, constructing and operating offshore wind projects globally."
Guy Madgwick, CEO of Red Rock Power Limited, added: "The completion of Beatrice signifies the monumental strides the Scottish offshore wind industry has made in recent years, and marks the beginning of a new chapter as we prepare to bring 30GW clean and affordable wind energy to consumers by 2030. Many of our team were responsible for securing Beatrice in the 2008 leasing round, and so after more than 10 years, we're delighted to see the development finally come to fruition."
Jim Smith added: "SSE Renewables has been involved in the offshore wind industry for 15 years now and we will take the learning from Beatrice and apply it as we now look to develop and deliver our pipeline of over 7GW offshore wind projects across the UK and Ireland.
"At the beginning of May, the UK Government's Committee on Climate Change determined that Britain would need to go faster and further to decarbonise. Beatrice is one demonstration of how SSE Renewables knowledge and expertise in developing, delivering and operating renewable energy assets can contribute to a zero-carbon world at scale."
Business Secretary Greg Clark: "The offshore wind sector is a UK success story, and the completion of this windfarm is further evidence that the UK is the best place to invest in renewable energy.
"In working with the government, the sector has shown it can deliver ever larger projects at ever lower costs while creating skilled, fulfilling, well-paid jobs. Our ground-breaking sector deal, signed earlier this year, will drive £250 million into businesses in the UK offshore wind supply chain – keeping the UK at the forefront of this vibrant 21st century industry."
Scotland's Energy Minister, Paul Wheelhouse, said: "The last of the 84 turbines being installed on Scotland's first commercial scale offshore wind farm is an important landmark for offshore wind in Scottish waters and a fantastic achievement for SSE and its project partners.
"In 2017, the Scottish low carbon and renewable energy sector supported over 46,000 jobs, and generated over £11 billion in turnover and, by the end of 2018, some 10.9GW of renewable capacity had been installed. This represents great progress and the offshore sector will make a growing contribution to mitigating climate change, and we are committed to ensuring that Scotland maximises the economic opportunity of an accelerating transition to a low-carbon economy.
"Projects like the 588MW Beatrice offshore wind farm will add to what is a growing industry for Scotland, and the project has already supported key supply chain businesses in Scotland, such as Global Energy Group, CS Wind and BiFab, among others. Projects such as this also have great potential for further economic benefit and job creation. The Scottish Government is determined to ensure the supply chain and economic benefits of this industry will be fully realised as we see consented sites built, and take forward further licensing opportunities to develop offshore wind in Scotland's waters."
Scottish Secretary David Mundell said: "I am pleased to see the completion of the Beatrice offshore wind farm, the largest of its kind in Scotland – providing enough electricity to power over 450,000 homes.
"The UK Government is committed to innovation in renewable energies including wind projects in Scotland. In March we launched the offshore wind sector deal, aiming to deliver a third of the UK's electricity through offshore wind by 2030. This is a fantastic example of unlocking that potential while also providing an abundance of quality and highly skilled jobs for the future."
Global Energy Group chairman, Roy MacGregor, said: "At Global Energy's Port of Nigg, we are very proud to have played our part in the delivery of SSE's first Scottish offshore wind farm, which is situated in the deepest water yet, for this type of development.
"This project justifies the huge investment we have made into our facilities and we are proud of our professional workforce who fully embraced the technical and operational challenge of successfully delivering our first major offshore wind project. We are pleased that our client Siemens and the project owners BOWL, have widely endorsed our good performance. We enjoyed an excellent working relationship with them both and now that we have proved our capability to deliver, we look forward to further contract awards in support of renewable energy developments around the coastline of Scotland and beyond."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...