Investigation works are due to begin ahead of construction on the Trams to Newhaven route later this month.
Ground and site investigation work has been programmed for a number of locations between York Place and Newhaven, starting in Lindsay Road in the week commencing 20 May 2019.
Separately - but planned in conjunction with these works - the Council's roads team will shortly be embarking on a major road resurfacing project in a number of streets surrounding the tram route.
The essential pre-enabling works programmed by the tram project's Systems and Infrastructure contractor Sacyr, Farrans, Neopul (SFN) will involve SFN carrying out detailed ground investigation works in 25 separate sites along the route. The work will be carried out in sections of approximately 100 metres at a time and is programmed to be completed by mid-July 2019.
The purpose of these ground investigation works is to determine the ground conditions along the length of the new tram route so that the project's final design can be confirmed.
SFN will check the ground conditions and depth of the bedrock along the route, for example to see how deep tram infrastructure foundations need to be, as well as the dimensions of the 'slab track' which will be laid under the tram track itself.
Meanwhile, the capital roads scheme works that are due to begin on Abercromby Place on 27 May have been brought forward from 2020 to make sure the road network surrounding the tram construction area is in good condition for when traffic diversions are put in place.
The work, part of the Council's investment in roads and footways across the city (£125m over five years), will include resurfacing the carriageway, pedestrian access and public realm improvements and traffic signal upgrades well as signalising the junction at Easter Road/Lochend Road and Duke Street.
Information about the ground/site investigation and road resurfacing projects will be communicated to directly-affected residents and businesses in advance of work starting.
Councillor Lesley Macinnes, Transport Convener, said: "There's going to be a fair bit of work going on in and around the Leith Walk area over the next few months and we're keen to make sure people have as much information as possible about what's happening and why. Both projects are aimed at helping the Trams to Newhaven construction phase go as smoothly as possible. We'll manage the works extremely closely to minimise noise and disturbance and we would like to thank residents in advance for their understanding while these essential projects are completed."
Alejandro Mendoza, SFN Project Director, explained: "These ground investigation works are vital to our early involvement. The information we obtain on the ground conditions will allow our design team to develop a robust final design. It will also help us inform key elements such as the construction plan and any effects that may have on traffic management arrangements."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
26/11/2024
Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024
The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024
First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024
A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024
Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024
The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024
West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024
Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024
Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024
Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...