An independent report into the Construction of the DG One Complex in Dumfries has been published.
The independent inquiry into the Construction of the DG One Complex was commissioned by Dumfries and Galloway Council in July 2017, after the discovery of significant building safety concerns and construction failures following a protracted dispute with the building contractor.
The inquiry, led by respected construction and procurement industry expert, Professor John Cole, CBE, presented their report at a Full Council Committee meeting today, 11 January.
The purpose and scope of the Inquiry contained 12 remits, which included:
• the rationale for the Council entering into the original design and build contract for the facility
• the contractual arrangements between Kier Northern and Dumfries and Galloway Council
• the role of the Council, professional consultants appointed to act for the Council and Kier Northern and their supply chain in relation to the quality assurance of the construction of the original building including the inspection process
• the Council's handling of the problems with the facility since 2009 including the process that led to the Council commencing proceedings against Kier Northern.
Professor Cole and the inquiry team had full access to all available knowledge and information relevant to the remit of the enquiry. This required the cooperation of a wide range of organisations, particularly those that had been directly involved in the original development of the DG One complex or in the subsequent investigations and remediation project.
The management of Kier Construction Scotland and North East (formerly Kier Northern) did not accept the invitation of the inquiry to send a representative and declined several requests to provide evidence.
Key findings from the report, which runs to over 350 pages, included:
• the contractors failure to provide the required standard of construction
• fundamental defects in the fire-proofing of the building
• defects to the masonry walls, significantly the inadequate installation of wall ties
• waterproofing the enclosing tanks and drainage connections of pools is a fundamental requirement when constructing a building with three internal swimming pools and a spa pool
• multiple failures on the part of the contractor to adequately comply with the requirements of the Building (Scotland) Act 2003
• inadequate arrangements made for the monitoring of the quality of works on site
• adequately resourcing projects with relevant professional expertise and funding would enable the Council to act as an intelligent and informed customer
The Inquiry report also provides advice and recommendations on any specific or wider lessons that can be learned from this project for Dumfries and Galloway Council and other public bodies.
Commenting on the report, Council Leader Elaine Murray, said: "We fully acknowledge all the inquiry's findings and thank Professor Cole and his inquiry team. The findings of his Inquiry give a damning verdict in the quality of construction of DG One at the hands of Keir Northern.
"Professor Cole's Inquiry contains a number of lessons and issues for the Council to reflect upon. There are also matters for the attention of Scottish and UK Governments. Dumfries and Galloway Council will be acting upon these immediately but legislative changes must also come in response to this Inquiry.
"I have previously referred DG One Leisure Complex to both the Health and Safety Executive and to Police Scotland. Police Scotland have previously indicated that if criminal activity is evident in the report they would be willing to take it further. Based on this, I will now refer the Inquiry Report to Police Scotland."
Commenting further, Depute Leader Rob Davidson, said: "The report highlights the fundamental failings in the construction of the DG One building were failings on the part of the design and build contractor. The Council had not unreasonably placed significant reliance on the size and experience of a major national contractor to deliver a building to the required standard."
Construction News
11/01/2019
DG One Build Inquiry


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip