Work to lift a new footbridge into place at West Calder railway station is now complete.
BAM Nuttall used a 300-tonne crane to lift nine sections of the structure, weighing more than 21 tonnes, into place on Sunday, 17 December.
The sections and staircases were connected to the lift towers which had been positioned earlier to complete the main frame of the structure. Works on the scheme will continue onto February 2018 and create step-free access across the railway, improving the station for people with impaired mobility, travelling with luggage, children or cycles.
Overall, the bridge forms part of Network Rail's wider work being delivered on the Shotts line ahead of the electrification of the route by March 2019.
Matthew Spence, Network Rail route delivery director, said: "Completing the installation of the main bridge structure is an important milestone for the project as we move towards making big improvements in accessibility at the station.
"Being able to build the new bridge sections at West Calder beside the railway and crane them into position enables us to deliver the work with the minimum disruption to the day-to-day operation of the station.
"We are continuously seeking opportunities to make stations more accessible. This new bridge will help ensure that everyone in the community has the opportunity to easily access services at West Calder station and thus enable even more people to travel by train."
(LM)
Construction News
19/12/2017
BAM Nuttall Lifts New Footbridge Into Place At West Calder Station


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont