Progress is continuing on plans to extend the Edinburgh tramline to Newhaven.
An Outline Business Case (OBC) has been approved by Councillors and work is now underway on the tendering process to secure a contractor for the project.
Construction work on the scheme is estimated to cost £165.2 million and is expected to take three years, including 18 months on Leith Walk, followed by around four months of testing and commissioning on new line.
A significant proportion of major utility works have already been carried out, with the remainder carried out in conjunction with main infrastructure works, meaning no ‘double dig'.
However, councillors will not make a final decision on taking the tram to Newhaven until autumn 2018.
The intervening period will enable the project team to:
• Allow affordability to be tested based on tender prices
• Provide a further 12 months of evidence of tram patronage build up; and
• Allow the project to consider any lessons learned from the Edinburgh Tram Inquiry currently under way
• Undertake detailed work on traffic management arrangements and measures to mitigate disruption for businesses and residents
Council Leader Adam McVey: "Given the rate of growth forecast for Edinburgh over the coming years, we simply cannot stand still. And yet we can't proceed with work to take trams down to Newhaven unless we're 100% certain we've rigorously scrutinised the business case and taken on board crucial lessons from the first phase.
"Having pored over the Outline Business Case in microscopic detail these past few weeks, including obtaining independent advice on it, I'm confident our project team - which retains key personnel from the team who got the first phase back on track - is now well placed to move on to the next stage and start the procurement process for a contractor.
"We will only make our final decision next autumn once the tendering process has completed and once we've consulted an independent assessor on the viability of the proposed construction contracts. We'll also of course consider any lessons learned from Lord Hardie's ongoing tram inquiry as we move forward."
(LM)
Time and date
CONSTRUCTION DIRECTORY
Construction News
22/09/2017
Progress Continues On Plans For Edinburgh Tramline Extension
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...