The City of Edinburgh Council has published the Outline Business Case (OBC) for taking Edinburgh's tram service down to Leith and Newhaven.
The comprehensive document sets out the findings and recommendations resulting from a 20-month programme of very detailed work assessing the benefits, impact and likely timescales and cost of completing the remaining 4.6km of tramline 1A.
The OBC has been available for councillors to scrutinise in a specially set up Data Room at the City Chambers, with officers and an independent advisor on hand to provide further information or clarify points.
A report accompanying the OBC will now be considered at a special meeting of the Transport and Environment Committee on 4 September, before going to Full Council on 21 September.
The report seeks authority to commence a procurement exercise to identify a potential contractor for the project, with a final decision on whether to go ahead with taking the tram to Newhaven, and with which contractor, to follow in autumn 2018.
Council Leader Adam McVey said: "Edinburgh is growing faster than any other city in Scotland and our current road network and public transport provision simply aren't sustainable given the number of new residents we're expecting to welcome here over the next two decades.
"Rather than exacerbating traffic problems on our already congested roads, trams allow far greater numbers of people to travel, while creating employment during construction, boosting development along the route and connecting people to centres of employment, leisure and retail."
Transport Convener Councillor Lesley Macinnes added: "Given the experience of the last tram project, we're acutely aware of the need to scrutinise this business case as rigorously as we possibly can – residents deserve nothing less. We won't take any decision on completing the line to Newhaven until we are 100% confident that the project can be delivered, financed and managed effectively.
"Councillors from all parties have been taking up the opportunity to fully examine the business case over the past weeks and will use this special meeting of the Transport and Environment Committee to quiz officers further on the detail and make a recommendation on whether to progress to the next stage."
Key points included in the OBC:
Rapid population and economic growth
• Over the next decade, Edinburgh and surrounding area expected to be home to faster growing population than anywhere else in Scotland. National Records of Scotland projections published in 2016 suggest city should be planning for an additional 47,000 people by 2024 and additional 102,000 by 2039 (20% increase)
• Number of households forecast to increase by over 38,000 (16%) by 2032. A quarter (25%) of this growth is forecast to occur in Leith Docks and Western Harbour area
• Employment levels in Edinburgh are projected to grow by 7.6% between 2013 and 2022
Costs & benefits
• Capital Cost estimated at £165.2m, including risk and inflation
• Patronage forecast to almost double in opening year to 14m, reflecting high population densities along the route
• For every £1 spent the economic return to the city is £1.64
• OBC includes wider economic benefits, including social inclusion, and completing the line will provide access to jobs and support business and opportunities in the area
Construction work to take three years
• Estimated three-year construction period, including 18 months on Leith Walk, followed by approx four months of testing and commissioning on new line.
• Significant proportion of major utility works have already been carried out – remainder carried out in conjunction with main infrastructure works, meaning no 'double dig'
• Carefully planned traffic management
• Diversions, road closures, access and crossing points thoroughly planned and modelled
• All key stakeholders, including residents, businesses, emergency services and Lothian Buses will be consulted on the traffic proposals set out in the OBC
Support for businesses
• Customer and service access to local businesses maintained at all times
• Compensation and support scheme for affected businesses along the route put in place
• Logistic centres and dedicated crossing points provided at 150-200m centres on Leith Walk
• Logistics officers deployed throughout the day to help businesses with deliveries
Lessons learned
• OBC recommends industry-standard contract with rigorous project governance
• Traffic management would give contractor expanded sites and provide flexibility if problems encountered
• Project would benefit from industry networking with other cities (Manchester, Birmingham, Dublin) to ensure best practice
• Consultation with the market and incorporating input from Tram Inquiry.
(MH)
Construction News
29/08/2017
Outline Business Case For Edinburgh Tram Expansion Published


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont