The £6.5 million fourth phase of the Bishopbriggs Relief Road project has been delayed until early next year, it has been announced.
Following a recent meeting between East Dunbartonshire Council and Network Rail, the local authority has confirmed the scheme's completion date has been pushed back to early 2018.
This is due to the need to relocate utility cables and ongoing wider works to deliver the Edinburgh Glasgow Improvement Programme (EGIP), which is being carried out by Network Rail.
The fourth phase of the road upgrade project is being delivered by Morrison Construction. It involves the creation of a new road between the end of Phase 3, at Wester Cleddens Roundabout, and a new roundabout near the Aviva offices on Westerhill Road. In addition, a new bridge is being created over the Edinburgh-Glasgow railway line as well as a new access road for Cadder Yard.
However, further work ongoing on the EGIP has delayed the installation of the new bridge.
Cllr Jim Gibbons said: "The Council is disappointed at the wider works outwith its control which are now impacting on the timing of the delivery of the road and fully share the frustrations of local residents and businesses.
"It is, however, essential to ensure that the relief road and the EGIP are delivered safely and that any issues which come to light, such as the need for utility relocation, are dealt with as they arise.
"Rest assured, we will continue to work with all parties involved - particularly Network Rail - to ensure any further delays are kept to a minimum wherever this is within our control and officers have escalated matters with our delivery partners.
"Based on the current programme for the installation of the bridge over the railway line, officers are advising that the road is programmed for completion by February next year."
(LM/MH)
Time and date
CONSTRUCTION DIRECTORY
Construction News
22/08/2017
Phase Four Of Bishopbriggs Relief Road Delayed Until Early 2018
Latest Construction News
26/11/2024
Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024
The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024
First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024
A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024
Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024
The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024
West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024
Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024
Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024
Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...