A programme of tower block structural surveys is to begin in North Lanarkshire.
The three-phase initiative will get underway on towers in Motherwell and Airdrie from Monday, 24 July.
Features include:
• Phase 1 - inspection of external condition of the buildings. All remaining 44 blocks (four already complete) will have selective external panels removed to inspect the condition of the buildings and cladding systems.. This work will be completed by early September.
• Phase 2 - internal inspection of selective buildings (as some buildings are of the same construction). This will include internal inspections in common areas, fire escapes, service routes and void spaces. This will also include some houses within the blocks. This work will be completed by the end of September/early October.
• Phase 3 - the remaining 44 tower blocks in North Lanarkshire will be given a full structural survey (four have already been surveyed). This could last up to 40 weeks starting from the end of September/ Early October.
The local authority added none of the cladding systems on tower blocks is the same as the type used at Grenfell tower and its insulation material is made of mineral wool which is non-combustible.
Council Leader Jim Logue said a planned survey programme for all towers was already in place, however as a result of the Grenfell tragedy the work has been brought forward.
"The safety of our tenants is paramount and we take our responsibilities as a landlord very seriously," he said.
"In June last year four blocks in Coatbridge were surveyed as part of a planned programme of investment works in residential towers.
"Over the coming weeks and months, a structural survey programme will take place to check that the buildings are in good structural order and to check if repairs are required to the cladding systems.
"This work will be undertaken by qualified structural engineers and, where essential repair works are identified, they will be carried out as quickly as possible."
Robert Steenson, Assistant Chief Executive, said: "We will write to tenants to inform them about the planned work and continue to meet with tenants groups to update them regarding the survey work and provide general information and fire safety advice.
"There will be minimum disruption to residents and their properties during the survey work and we expect the initial phase of work to be completed within a few weeks.
"Once the exterior surveys have been completed we will then carry out internal structural surveys, before full structural surveys take place on all blocks from the end of September."
(LM/MH)
Construction News
19/07/2017
Structural Tower Block Surveys To Begin In North Lanarkshire


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont