A major milestone has been reached on a £17 million environmental project in Paisley.
A Microtunnel Boring Machine (MTBM) has started work to build a one mile-long waste water tunnel/sewer as part of the scheme, which will improve the water quality and natural environment in two local rivers.
Contractors Amey will develop the large diameter interceptor sewer, starting at Bridge Street car park and going across the Watermill Hotel car park and Lonend before going along Saucel Street, beneath Saucelhill Park and the railway line near Canal Street Station, Espedair Street, Rowan Street and Kilncroft Lane/Neilston Road.
The 'Abbey' MTBM was launched at one of the 15 shafts along the tunnel route and will install the first third of the tunnel. The structure will be 1200 milimetres in diameter, while two other machines will install the second and third stretches of the tunnel, which will be 1500 milimetres and 1000 milimetres in diameter.
Removing around 45 – 50 tonnes of earth per day, the tunnel will be installed by the pipe jacking method with individual sections of concrete pipe installed sequentially and jacked into position to the rear of the MTBM once the machine has removed the soil. It will be installed mainly in mudstone and siltstone. Overall, the new stretch of sewer will have a diameter of up to 1.5 metres and will be installed at depths of between 4m and 20m.
Brian Boland, the project manager, said: "We are delighted to have reached this milestone on the project, after a lot of preparatory work, and to have lowered the tunnel boring machine onto position at the launch chamber.
"Once it was assembled below ground, the machine was presented to the rock face and has now started its work on boring through the earth and installing the pipe. After four years of planning this project, in liaison with the Scottish Environment Protection Agency (SEPA) and Renfrewshire Council, it is great that the tunnelling proper is now under way."
The £17m project also includes the installation of Combined Sewer Overflows (CSOs) in the town centre, reducing the frequency of spills from the sewer network into the Espedair Burn and White Cart Water in storm conditions.
The investment is part of Scottish Water's £250m, five-year programme of work to improve river water quality and the natural environment and tackle flooding across the Greater Glasgow area.
Work on the project started last October and is expected to take two years to complete.
(LM/MH)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...