Interserve has reported a £94.1 million loss in its annual results for the year ended 31 December 2016.
With revenue remaining at £3.2 billion, the major loss is due to the company making a £160m provision as its exits the energy from waste sector.
Last year, Interserve was removed from the Glasgow Recycling and Renewable Energy project due to project delays.
The Board announced an exceptional provision of £70m in May the same year to cover exit costs. However, costs associated by exiting the project have proved far worse than expected.
In addition, the company's UK construction division suffered a £3m operating loss due to "challenging market conditions, coupled with pockets of underperformance in operational delivery in a number of contracts".
However, with a future workload of £7.6bn, and particularly strong growth in international construction, Chief Executive Adrian Ringrose said 2016 was a "mixed year" for the Group.
"We delivered a strong cash performance and the majority of our businesses performed well despite political and economic uncertainties, together with the impact of the National Living Wage in the UK. However, the performance of our UK Construction business was disappointing, and we are focussing our efforts on improving and re-shaping this business.
"Managing the challenges of exiting from the Energy from Waste sector remains a significant priority. As previously announced, we have increased the exceptional provision for exiting this market and the associated contracts to £160 million. We expect to complete substantially all of the construction and commissioning of the projects during 2017, although our contractual obligations in respect of warranties, and the resolution of claims will continue for a period thereafter.
"While liquidity available to the group is adequate, having put in place new banking facilities that expand and extend our debt capacity, the Board has a medium term objective to reduce our overall indebtedness and enhance liquidity levels further whilst continuing to invest in our core businesses. We have therefore taken the difficult decision to suspend the dividend temporarily.
"Despite the increased uncertainty following the UK's EU referendum, our outlook for the current year remains positive. This, together with our strong market positions and healthy future workload, underpins the Board's confidence in our medium term prospects."
(LM/MH)
Construction News
28/02/2017
£94.1m Loss Reported By Interserve


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont