A major milestone has been reached on Scottish Hydro Electric (SHE) Transmission's £1.1 billion Caithness-Moray project.
Four cable ducts have been developed through the rock beneath Noss Head, north of Wick, almost 500 metres out to sea.
The ducts were drilled as part of the installation of the 100-mile High Voltage Direct Current (HVDC) link between Spittal in central Caithness and Blackhillock in Moray. Cables will be pulled through the ducts on to land next year once drilling work has been completed and when marine installation work is to take place.
Main electricity cables will be installed in two of the four ducts, while a third duct will contain fibre optic cable used in the operation of the system.
Once completed, the HVDC will enable up to 1,200MW of renewable power to be transferred beneath the Moray Firth.
SHE Transmission's Lead Project Manager for onshore cable works Michael Blake said: "The successful completion of the drill at Noss Head is a major achievement for our project – and particularly for the team that has been working hard on site over the past few months.
"The main onshore cable works are now nearing completion in Caithness and the ducts at Noss Head will enable the first stage of the cable’s journey beneath the Moray Firth."
(LM/CD)
Construction News
20/07/2016
Major Milestone Reached On £1.1bn Caithness-Moray Project


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont