The West Coast Mainline is due to reopen next week, the ScotRail Alliance has announced.
The route was originally closed at the start of the year as the Lamington Viaduct was damaged by floods caused by Storm Frank.
Train services will resume running on Monday, 22 February.
Works to repair and reopen the Victorian-built viaduct have been taking place over the past seven weeks.
The structure had to be stabilised after the storm, which also damaged the second pier's steel bearings.
Engineers have now installed new steel bearings on the viaduct's damaged second pier and developed a new concrete plinth on the top of the pier over the weekend.
Having successfully raised the bridge-deck back into position last week, the recovery works are now progressing two weeks ahead of the original reopening date in March.
Phil Verster, MD of the ScotRail alliance, said: "I am delighted that we have managed to complete the works at Lamington ahead of schedule.
"I understand the impact the closure of Lamington Viaduct has had on customers and our engineers have been working around-the-clock since its closure to finish the repairs and get trains back on the West Coast Mainline.
"This project has been a hugely challenging one - involving working out in the Clyde through the worst of January's storms in a race against time to save the structure. Our engineers have faced atrocious conditions throughout this project and I am really proud of their hard work and their absolute commitment to getting the line open again."
(LM)
Construction News
15/02/2016
West Coast Mainline To Reopen Next Week


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont