Engineers have designed a solution for repairing structural issues on the Forth Road Bridge, it has been announced.
A team of engineers from Amey developed the plans after a crack appeared on one of the bridge's truss end links.
It is understood the bridge will remain closed until the new year.
The repair designs have now been finalised, checked and verified by two independent specialist engineering firms.
Work is now underway to build an access platform to carry out the repairs.
The project will involve a plate welded repair to the damaged truss end link and jacking the link into position.
In addition, Amey is taking preventative action on another seven similar locations on the bridge to prevent any issues from occuring and structural monitoring systems are also being installed at these locations.
Chartered Engineer Mark Arndt, Amey's Account Director, said: "Our teams have been working 24/7 since the defect was identified a little over a week ago.
"Our design teams have finalised the detailed solution plan, the access platform is under construction and we've mobilised all the resources we need to begin the repair works.
"Progress of the repair work is vulnerable to weather conditions. Wind speeds at times make it unsafe for our people to continue but by having our personnel on standby at the bridge and by monitoring live wind-speed data in our control room we're able to get straight back out to work on the repairs in every available window and our programme remains on schedule for completion in the New Year."
Transport Minister Derek Mackay added: "Our priority is to get the Forth Road Bridge operating as soon as possible and our engineers are doing all they can to make that possible.
"They are working tirelessly on designs for the repair and are putting the equipment they need in place so that it can be completed in good time.
"It is difficult and technical work and the team is to be commended on its commitment to getting the job completed despite the weather conditions."
(LM/JP)
Construction News
10/12/2015
Engineers Design Repair Solution For Forth Road Bridge


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont