Anglo-Scottish Interconnector Approved

Planning consent has been granted for a change to the electricity grid that will allow new renewables developments to be connected to the grid.

Energy Minister Fergus Ewing has approved a change to the route of the existing Anglo-Scottish Interconnector 400 kilo Volt (kV) overhead electricity transmission line at Bearholm near Moffat.

The change will move 1.8km of the existing line to connect the Moffat substation at Bearholm to the transmission grid. The substation will provide a connection for renewables developments in the Moffat area including the Harestanes (Forest of Ae) wind farm. Five existing 46 metre high towers will be replaced with five new towers of the same height.
-- Advertisement --
NorthernAsbestosServicesLtd



Energy Minister Fergus Ewing said: "The new route of the Anglo-Scottish interconnector will allow new renewable energy developments to connect to the grid.

"These developments will produce jobs for the local area, save thousands of tonnes of carbon dioxide and power thousands of homes.

"In consenting this application I have put conditions in place which will protect local communities and wildlife. I am confident that this change to the interconnector will enable renewable energy developments which will provide great benefits to the local community and play an important part in helping Scotland reach its target of the equivalent of 100 per cent of electricity demand generated from renewables."

Developers SP Transmission Ltd applied to the Scottish Government in June 2007 for a change to the existing Anglo-Scottish Interconnector 400kV overhead electricity transmission line. One representation was received from a member of the public, who objected because at the time of the application, the Harestanes wind farm had not received consent. It was consented on September 10, 2007.

(GK)

Latest Construction News

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment. The pane
15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire. The event will take place on Monday, 28 April, from 4 pm t
15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle. This key appointment will enable crucial work to progress on the project, including feasibility s
15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027. The £5 million
15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment. The practical guide is designed for landowners, developers,
15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it
14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year. The initial grant of £78.687 million from the Scottish Government
14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure. From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont
RBT Underfloor LimitedMorris & Spottiswood LtdForde Training Services LtdPlant Glazing LtdThe Water PointCRGP LimitedM&C McLean LtdStoneCleanScotland.co.ukDunedin Stone LtdSEEIT3D