The painting of the Forth Bridge is set to finish in December.
Balfour Beatty Regional Civil Engineering is currently carrying out the project.
After 10 years and an investment of over £130m, scaffolding can finally be removed from the bridge and a full paint job will not be required again for over twenty years.
The current contract should be completed ahead of schedule on Friday 9 December 2011.
The current project involves erecting scaffolding access, screening it off from the environment and using an abrasive blasting technique to remove old layers of paint applied over the last 120 years.
Steelwork requiring maintenance is then repaired before the new paint is applied in three protective layers.
Managing director of Balfour Beatty Regional Civil Engineering, Marshall Scott, said: "Balfour Beatty is delighted to have played such a significant part in the restoration of the iconic Forth Bridge over the last 10 years.
"By working together in a close relationship, Balfour Beatty Regional Civil Engineering, Network Rail, the principal subcontractors and the workforce involved in undertaking this complex programme of restoration have successfully delivered a project requiring safe systems of work to overcome some of the most difficult of working conditions.
"The now fully restored Forth Bridge will continue to operate for many decades to come and it will provide the world renowned image that Scotland can be rightfully proud.
"The work that Balfour Beatty Regional Civil Engineering has provided to restore the Forth Bridge back to its original condition will remain as part of a legacy and a testament to the skills and expertise of those who built this much treasured structure more than a century ago."
Route managing director of Network Rail Scotland, David Simpson, commented: "Network Rail is the proud steward of our railway history, which the Forth Bridge exemplifies. Since 1890 it has been a working monument to the genius of British railway engineering. Over the last decade, the bridge has been restored to its original condition and its new paint will preserve the steelwork for decades to come.
"The current restoration work has been ongoing since 2002 but, owing to years of underinvestment during the 70s and 80s, the scale of the job was initially unclear. Now, with scaffolding being removed and the final sections of painting being completed, we're confident that job will be finished before Christmas.
"The paint system being used on the bridge has been used in the past on north sea oil rigs. We expect it to last in excess of twenty years but we will be back from time to time to maintain the most exposed sections of the structure."
A celebration event to mark the end of the refurbishment will take place in March 2012.
(JG/GK)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...