Angus Council is making progress with the £3million project to realign the A92 at Hawkhill and Courthill bends.
The purchase of the pieces of land needed for the realigned stretch of the road known locally as Big Tree bends is nearing completion and a contract for the construction works is due to be awarded in August.
The council’s roads spokesperson councillor David Fairweather welcomed the progress being made saying: “I’m delighted to see this project moving on. It’s a significant investment that will be welcomed by motorists as it will really improve this stretch of the A92.
“Nine companies have been invited to tender for the construction work and those tenders are due back in on 11 August. Work should then be able to start in the autumn and be completed by next summer.”
Councillor Mark Salmond, the council’s finance and property spokesperson, said: “Although the negotiations over the required land took a bit longer than we’d originally expected it’s good to see the progress that’s now been made. The various property transactions are just being finalised so there should be no problems with work starting in the next couple of months.
“I know from the representations made to me and other elected members over the years that the news that the project is about to start will be welcomed by those who regularly use this route.”
Two project reports will be considered by the council’s executive sub committees for Infrastructure Services and Corporate Services next Tuesday, 26 July.
(GK)
Construction News
01/08/2011
£3m Big Tree Bends Project Progress

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont