M74 Extension Opens

The new M74 motorway will open to open to traffic today.

Cabinet Secretary for Infrastructure and Capital Investment Alex Neil said that the new motorway will generate as many as 20,000 jobs for the Scottish economy.

The improved transport link, completed by between £15 - £20 million under budget, supported 900 jobs during its three year construction.

Completed eight months ahead of schedule, the M74 is expected to take around 20,000 vehicles per day off the M8 reducing peak hour journey times by up to 10 minutes.

Mr Neil said: "The new M74 motorway will bring major economic and social benefits to businesses, communities and industry in the West of Scotland and the country as a whole.

"Thousands of new jobs will be created and because this crucial piece of infrastructure was completed several months ahead of schedule, millions of pounds of Scottish taxpayers' money has been saved.

"The daily rush hour congestion in and around Glasgow will also be eased leading to improved travel, which is good news for business, commuters and the many thousands of visitors coming to Scotland."

Interlink M74 JV Chairman, Bob Wilson, said: "Interlink M74 JV is delighted to have successfully delivered the design and construction of the M74 Completion project, Scotland's largest single road scheme in a generation. The opening today is a great day for everyone involved with the project and the wider Scottish construction industry.

"Throughout the three year construction period, Interlink M74 JV, a joint venture between Morrison Construction, Balfour Beatty, Morgan Sindall and Sir Robert McAlpine, has worked closely with its customers, subcontractors and suppliers. Together, we have delivered this complex civil engineering project safely, ahead of programme and on course to be under budget.

-- Advertisement --
NorthernAsbestosServicesLtd

"This is a testament to the ability of all those in the project team, and demonstrates what commitment, cooperation and teamwork can really achieve on a project of this scale.

"The project team has repeatedly been acknowledged for the high standard of its management and contribution to the environment and local community. The project has been able to employ a high proportion of local people creating over 50 employment opportunities for the long term unemployed."

Councillor Gordon Matheson, Leader of Glasgow City Council, said: "This is a momentous day for Glasgow and for Scotland.

"We have completed the M74 - a vital part of the west of Scotland's motorway network and an important project for the future growth of the economies of both Glasgow and the country.

"This road is of major significance to the city. For years, Glasgow made the case for the completion of the M74 and since day one has been the force behind the project. The council staff have worked tirelessly to get the road finished ahead of time and under budget. Its completion will bring opportunities for thousands of individuals and businesses, support East End regeneration, and help us deliver the best possible Glasgow 2014 Commonwealth Games.

"Today marks the start of a new era for Glasgow and the west of Scotland with an enhanced transport infrastructure, ensuring the city is better connected both nationally and internationally, and ensuring easier access to, from and across Glasgow."

The M74 Completion project is a partnership between Transport Scotland, the principal funder, and Glasgow City, South Lanarkshire and Renfrewshire Councils and the contractor is Interlink M74 JV, a joint venture comprising Morrison Construction, Balfour Beatty, Morgan Sindall and Sir Robert McAlpine, four of the UK's major civil engineering contractors. The project has a fixed construction cost of £445 million plus an allowance of £12 million for treatment of mine workings along the route.

The M74 Completion project completes the missing link between the end of the M74 at Fullarton Road junction near Carmyle, and the M8 motorway west of Kingston Bridge, on the south side of Glasgow City centre and the River Clyde.

The new stretch of motorway will be five miles (8km) long comprising a dual three-lane carriageway with hardshoulder reducing to two lanes between the Kingston junction and the connections to the M8. Four grade-separated junctions have been constructed; at Kingston, Polmadie Road, Cambuslang Road and Fullarton Road.

(GK/KMcA)

Latest Construction News

22/11/2024

SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024

Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024

Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024

A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024

The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024

South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024

SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024

Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024

Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024

Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...
RBT Underfloor LimitedMorris & Spottiswood LtdSEEIT3DCF Concrete PumpingMaccaferri LtdDiscount Kitchens and Bathrooms LtdShopfronts ScotlandJSJ Foam Insulation LtdEarth Tech LPS LTDSolway Ecology Consulting Ltd
Terms and Conditions
2024/11/23 08:58:38