The way forward for the tram project is clearer today with one of the proposals agreed through the mediation process being made public.
Following the mutually agreed appointment of an independent mediator, Michael Shane, intensive meetings took place from 8 - 12 March with all relevant parties represented. In the two months since, positive dialogue has been maintained.
A key outcome of the process has been that the parties have set aside their differences in respect of Princes Street and the infrastructure contractor, Bilfinger Berger and Siemens (BBS) has agreed that it will carry out a programme of remedial works to fully repair the road surface. The works will be carried out in two stages: from 3 July - 26 November and then from January - May next year. No new public funds will be required for these works.
Other works on Princes Street will also be undertaken including erecting street lighting and remaining overhead line equipment poles and work around the tram stop.
Over the coming period, prior to the diversions being implemented, the Council and the infrastructure contractor will carry out a detailed consultation with the city centre business community, and other key stakeholders, to plan the necessary arrangements for traffic diversions, bus services, pedestrian routes, waste collection, deliveries and signage.
Traffic diversion arrangements will be broadly similar to those in place during previous works, with buses, taxis and cycles diverted to George Street and general traffic diverted onto Queen Street as a principal route.
Leader of the City of Edinburgh Council, Cllr Jenny Dawe, said: "Last November I instructed the Chief Executive to pursue the option of mediation with tie and the infrastructure contractor and I am pleased that we are now seeing the benefits of this process.
"Without question there is a difficult period ahead, however I am still of the belief that a tram network which expands over time will be of enormous benefit to people living and working in this city for generations to come.
"The programme of priority works along with rectifying the road surface and other works on Princes Street is a sign that we are moving forward. We had hoped to avoid the scenario of a further traffic diversion from Princes Street but having listened to the advice from council officers and the infrastructure contractor I understand why this is necessary. We will work closely with the city's business community to ensure any impact is managed effectively before the diversion is put in place and during the period of works."
Vic Emery, Chair of tie, added: "It was vital that the momentum of the project was restored. All parties involved are in agreement that, through the mediation process, good progress has been made in identifying the key issues that lay at the heart of the dispute, and a measure of goodwill has been re-established.
"The next step is to finalise the revised plans for the delivery of phase 1a, including projected costs and programme, and this will be shared with all relevant parties including Transport Scotland and the Scottish Government before being made public in due course."
Martin Foerder, Project Director for Bilfinger Berger Civil UK Ltd commented: "There are a number of outstanding elements still to be undertaken on Princes Street and by doing these now we are also able to repair the road surface.
"Bilfinger Berger, Siemens and CAF are committed to working with partners in Edinburgh to deliver a tram system for the city and have already completed a number of significant structures as well as the building of the tram vehicles.
"I look forward to being able to announce shortly the plans for the remaining works still to be undertaken which will see trams running from the airport to the city centre."
A full programme of consultation with city stakeholders affected by the Princes Street programme will be undertaken, including an analysis of any opportunities which may arise to use the increased availability of pedestrian space.
(GK)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...