Dounreay Site Restoration Limited has announced Graham Construction as its preferred bidder for the design and build of a low-level radioactive waste disposal facility, which was chosen after a competitive tendering exercise from a short-list of five companies.
Subject to NDA approval and completion of a number of procedures, the contract award is expected by the end of March.
The development is an essential part of the infrastructure needed to complete the decommissioning and closure of the former nuclear research site.
The contract is for the design and construction of two sub-surface vaults for the disposal of solid low-level radioactive waste from the site clean-up. It will be based on target cost design and build contract under the NEC conditions.
DSRL has planning consent for up to six vaults adjacent to the site but hopes to reduce the number that need to be built through waste minimisation practices in decommissioning.
Up to 100 jobs will be created during the construction phase, with a quarter of the work expected to be sub-contracted to local companies. The Nuclear Decommissioning Authority will invest up to £4 million in a community benefit fund associated with the development
Subject to regulatory and other consents, construction is scheduled to begin in autumn 2011 and take two years to complete.
The lifetime cost of the development is expected to be in the region of £100m.
Audrey Cooper, project manager at DSRL, said: “The design stage of the work is an opportunity to improve the scheme and take into account valuable feedback from local stakeholders, while still working within the constraints of the planning consent.
“I expect the first two vaults to be completed by mid-2013, which is two years earlier than previously indicated.”
Leo Martin, director at Graham Construction, said: “We are delighted to be announced as preferred bidder on this contract. This is a very important project for us, in a market sector which we are looking to expand into further. We are very much looking forward to delivering this important project for DSRL.”
(GK)
Construction News
24/01/2011
Low-level Radioactive Waste Contract For Civils

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont