Progress continues on the M74 Completion project with the successful erection of beams at Glasgow Road underbridge.
The operation took place over two weekends in October and November using a crane to place the 39 precast concrete beams onto the structure.
Placed end to end, the beams used to construct the bridge would fit down both sides of Rutherglen Main Street.
Work was carried out in three stages with each of the side spans being constructed first using a total of twenty beams, each almost 23 metres long.
The beams to form the central span, which passes over Glasgow Road, were then craned into place.
Each of the nineteen beams required for this central span are almost 34 metres in length and 1.6 metres deep.
The Glasgow Road underbridge is one of thirteen bridges along the route of the new motorway and will carry the M74 over Glasgow Road.
The bridge is supported at each end by reinforced concrete abutments and at two intermediate points by reinforced concrete columns.
Now that the beams are in place, the reinforced concrete deck will be cast on top of the beams over the coming months. Thereafter, parapet construction and bridge deck waterproofing will be carried out, followed soon after by tarmac road construction.
Dominic Murphy, Project Manager for Transport Scotland, the major funder for the project on behalf of the Scottish government, commented on the progress: "I am pleased that Interlink M74 JV's work to erect the beams at Glasgow Road went smoothly and, despite the inclement weather, was completed well within schedule.
"Residents in the Rutherglen area will be seeing real progress on the M74 Completion, particularly at each of the bridges at Rutherglen Station, Glasgow Road and Cambuslang Road, in the coming months. The side span beams for the Cambuslang Road bridge are due to be erected later this month and Glasgow Road underbridge is scheduled for completion in autumn 2010.
"The M74 Completion will reduce traffic from the local roads in the Rutherglen area alleviating congestion, improving air quality and reducing the number of accidents. On a wider scale it will provide significant benefits, both economic and social, to businesses, communities and industry throughout the West of Scotland."
Chair of South Lanarkshire Council's Enterprise Resources Committee, Councillor Chris Thompson, said: "The progress being made on the M74 is fantastic and people can really begin to see the completion project taking shape before their eyes.
"A huge amount of credit has to be given to the contractor, Interlink M74 JV, for managing to erect the beams despite the terrible weather conditions they were faced with.
"The completion of the M74 will bring with it huge benefits to people throughout the west of Scotland."
(GK/KMcA)
Construction News
30/11/2009
Glasgow Road Bridge Beams In Place
.jpg)

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont