The organisers of the Commonwealth Games are making progress in a number of key areas but now need to put in place an overall programme plan, ensure costs are under control and continue to identify and manage other risks, according to Audit Scotland.
The progress report on planning for the delivery of the Commonwealth Games 2014, says the main organisers, (Commonwealth Games Scotland, the Scottish Government, Glasgow City Council and Glasgow 2014 Ltd) need to continue to actively identify and manage the risks through to 2014 and beyond.
The particular challenges for the Games organisers include: the immovable deadline; the complexities caused by the number of partners involved; and the importance of establishing contingency arrangements, such as in the event of poor weather.
The report says the organisers are making progress in developing plans for their specific areas of responsibility, such as building the venues, security, ticketing and sponsorship. However, delivering the Games is complex, and although there are almost five years to go before the Games take place, it is vital that these separate plans are pulled together very soon so that they are properly managed and coordinated.
The report highlights that the top risk is that costs could rise. Earlier this week it was announced that the Games budget has been increased by £81 million from £373 million to £454 million.
Over and above the Games budget, a further £269 million is being spent on developing 15 venues that will be used for the Games and around £1.6 billion is being spent on improving transport infrastructure. These projects were planned before the bid and are not a cost of the Games. In addition, private developers are expected to meet the costs of constructing the Athletes’ Games Village.
Caroline Gardner, Deputy Auditor General, said: "The Commonwealth Games is a major event for Scotland and attention to detailed planning at this stage is an essential part of contributing to its success. Our report highlighted a potential shortfall in the budget as a risk.
"Earlier this week the Games budget was increased to £454 million. In the current economic climate public sector finances are already under pressure and it is essential that the organisers keep costs under control. They need to continue to monitor and review the budget assumptions regularly."
The report includes lists of the venues and transport projects, with planned completion dates matched against recent information. Although there has been some slippage, all the Games related venues and transport infrastructure projects are currently on course to be delivered in time for the Games.
John Baillie, Chair of the Accounts Commission, said: "Although a key feature of the bid was that 70% of the infrastructure, including venues, was already in place, delivering a high quality Commonwealth Games to a fixed deadline presents major challenges for the four main organisers. It is crucial that risks are well managed as plans progress towards hosting the Games in 2014."
(GK/BMcC)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...