Demolition of a bridge as part of the major new motorway scheme improving the link between Glasgow and Stirling has been completed ahead of schedule.
The A80 North Road Bridge demolition works were originally planned to be carried out over two weekends, 9th and 16th October 2009, but were finished safely and successfully within two nights by Transport Scotland’s contractors Highway Management Construction (HMC).
The works included overnight road closures and reduced running lanes on the A80 during the day to allow HMC safe site access and control of the demolition.
Michelle Rennie, Head of Branch, Transport Scotland said: "We are pleased to see this significant milestone in the M80 project completed ahead of schedule. Transport Scotland strives to minimise disruption to road users and HMC has been instrumental in supporting this through their quick and efficient works."
Early completion of the works means that the anticipated closures of the A80 next weekend will not be required.
Transport Scotland and HMC would like to thank all construction personnel for their hard work, North Lanarkshire Council for their co-operation, the local residents, and the travelling public for their patience whilst these essential works were carried out.
The A80 is an essential part of the trunk road network in central Scotland and one of the most heavily used. The M80 Stepps to Haggs project will complete the missing gap between Stirling and Glasgow bringing real benefits to the surrounding communities across the central belt as a whole.
(GK/BMcc)
Construction News
14/10/2009
A80 Bridge Demolition Completed Early
.jpg)

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont